Permit: DP21-0115
Permit Details
Apply Date:
05/03/2021
Applicant:
Description:
SITE: Maddock Machinery. Building demolition and addition.
Permit Reviews
Permit Number - DP21-0115
Permit Status: Complete
Permit Description: SITE: Maddock Machinery. Building demolition and addition.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/17/2022 | DEV PKG - OK TO SUBMIT | 03/10/2022 | COMPLETED |
| 03/10/2022 | REVISION - - 1ST | 04/04/2022 | COMPLETED |
| 05/03/2021 | DEV PKG - OK TO SUBMIT | 05/07/2021 | COMPLETED |
| 05/07/2021 | DEV PKG | 06/18/2021 | COMPLETED |
| 07/19/2021 | DEV PKG - RESUBMITTAL | 09/08/2021 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0115
Permit Description: SITE: Maddock Machinery. Building demolition and addition.
Total Completed Inspections - 4
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/26/2022 | ENGR Engineering Final | Passed | {Activity date: 05/26/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - APPROVED} | |
| 05/26/2022 | SITE - Stormwater Follow-up | Passed | {Activity date: 05/26/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - APPROVED} ; {Activity date: 04/29/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED NO CONCERNS AT THIS TIME} ; {Activity date: 04/14/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /NO CONCERNS.} ; {Activity date: 03/30/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN / NO CONCERNS AT IS TIME.} ; {Activity date: 03/15/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN NO CONCERNS AT IS TIME} ; {Activity date: 02/25/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - CONTINUED, NO CONCERNS AT THIS TIME} ; {Activity date: 02/01/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS CONTINUED, NO CONCERNS AT THIS TIME.} | |
| 06/02/2022 | SITE - Zoning Final | Passed | {Activity date: 06/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by DROBERT5 - } | |
| 06/02/2022 | ENGR Grading Final | Passed | {Activity date: 06/02/2022; Status: Approved; Inspector: MHERNANDEZ; Comment: Entered by DROBERT5 - } ; {Activity date: 10/06/2021; Status: Not Applicable; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - NA / NO CONSTRUCTION. YET WILL START ON NOVEMBER FIRST?} |