Permit: DP21-0069
Permit Details
Apply Date:
03/17/2021
Applicant:
Description:
SITE - Pascua Yaqui Tribe, Senor de Los Milagros. Civil improvement and utility connection. Three ne
Permit Reviews
Permit Number - DP21-0069
Permit Status: Issued
Permit Description: SITE - Pascua Yaqui Tribe, Senor de Los Milagros. Civil improvement and utility connection. Three ne
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 03/17/2021 | DEV PKG - OK TO SUBMIT | 03/26/2021 | COMPLETED |
| 03/26/2021 | DEV PKG | 04/21/2021 | COMPLETED |
| 05/03/2021 | DEV PKG - RESUBMITTAL | 05/07/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP21-0069
Permite Description: SITE - Pascua Yaqui Tribe, Senor de Los Milagros. Civil improvement and utility connection. Three ne
Total Outstanding Inspections - 5
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/17/2022 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 05/17/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN /INFORMED THE CONTRACTOR TO WET THE GROUND FOR DUST CONTROL. } ; {Activity date: 05/03/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN/ INSTALLED THE WATTLES ON THE NORTH END OF PROJECT.} |
| 11/08/2022 | ENGR Engineering Final | N/A | Not Ready | Not ready for final inspection |
| 11/08/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | Contractors not ready for inspection |
| 06/07/2023 | ENGR Grading Final | N/A | Complete (Recurring) | Contractors good to grout the last 4 foot of the trash enclosure |
| 05/24/2023 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | Contractor set rebar for trashing closure on the southwest side of the building |
Completed Inspections
Permit Status: Issued
Permit Number: DP21-0069
Permit Description: SITE - Pascua Yaqui Tribe, Senor de Los Milagros. Civil improvement and utility connection. Three ne
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/19/2024 | COT - ENGR - Signage Final | Passed | ||
| 01/19/2024 | ENGR Engineering Final | Passed | ||
| 01/19/2024 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 01/19/2024 | PDSD Site/Engineering Division - NPPO | Passed | ||
| 01/19/2024 | ENGR Grading Final | Passed | ||
| 01/19/2024 | PDSD Engineering Division Pre-Construction SITE | Passed | ||
| 02/22/2024 | SITE - Stormwater Final Inspection | Passed |