Inspection Status: Not Ready
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 10/27/2022 |
ENGR Grading Final |
|
Not Ready |
|
| 04/27/2022 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN / NEED TO PLACE WATTLES ALONG THE FENCE LINE..
|
| 10/12/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by RSALDAT1 - Na |
| 01/19/2024 |
ENGR Grading Final |
|
Passed |
|
| 01/19/2024 |
ENGR Grading Final |
|
Passed |
|
| 01/19/2024 |
ENGR Grading Final |
|
Passed |
|
| 05/24/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Contractor set the rebar for trash enclosure the southwest side of the building |
| 06/05/2023 |
ENGR Grading Final |
|
Partial Pass |
I inspected the trash enclosure to see if it was ready for grout and contacted Dreiser construction and advise them. They could go ahead and grab the first 4 feet of the trash and closure walls. |
| 06/07/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Contractors good to grout the last 4 foot of the trash enclosure |
| 06/12/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Contract grout the top for the trash enclosure and now they’re going to Cap it . |
| 06/13/2023 |
ENGR Grading Final |
|
Complete (Recurring) |
Set the steel for the floor for the trash enclosure good to pour |
| 07/18/2023 |
ENGR Grading Final |
|
Partial Pass |
I’m still a little more grading on the north end of the building that needs to be completed |