Permit: DP21-0019
Permit Details
Apply Date:
01/22/2021
Applicant:
Description:
SITE/GRADING - Salad and Go at The Bridges, new restaurant.
Permit Reviews
Permit Number - DP21-0019
Permit Status: Complete
Permit Description: SITE/GRADING - Salad and Go at The Bridges, new restaurant.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/22/2021 | DEV PKG - OK TO SUBMIT | 01/28/2021 | COMPLETED |
01/28/2021 | DEV PKG | 03/12/2021 | COMPLETED |
04/07/2021 | DEV PKG - RESUBMITTAL | 05/04/2021 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP21-0019
Permit Description: SITE/GRADING - Salad and Go at The Bridges, new restaurant.
Total Completed Inspections - 7
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/10/2021 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 12/10/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by VVERA1 - IS APPROVED} | |
12/10/2021 | TRSP - ROW - Final/Close-Out | Passed | {Activity date: 12/10/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
12/10/2021 | SITE - Stormwater Follow-up | Passed | {Activity date: 12/10/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 09/03/2021; Status: Continued; Inspector: DROBERTS; Comment: Entered by VVERA1 - 9154 (STORMWATER FOLLOW-UP INSP) NO CONCERNS AT THIS TIME} | |
12/10/2021 | ENGR Grading Final | Passed | {Activity date: 12/10/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
12/10/2021 | COT - ENGR - Signage Final | Passed | {Activity date: 12/10/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
01/04/2022 | SITE - Zoning Final | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
01/04/2022 | ENGR Engineering Final | Passed | {Activity date: 01/04/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 12/10/2021; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - PENDING MINOR CONCRETE SIDWAL REPLACEMENT} |