Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 12/10/2021 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 12/10/2021 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 12/10/2021 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 09/03/2021 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by VVERA1 - 9185 (GRADING - INTERMEDIATE) THE CREW IS WORKING ON THE INSTALLATION OF THE REINFORCED CONCRETE PIP FOR THIS SITE AND HAVE BEEN APPROVED FOR BACKFILL PLACEMENT AT THIS TIME. |
| 12/10/2021 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 10/04/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN/ FOR TRASH BIN NEED KNOCKOUT FOR THE GROUTING . |
| 09/28/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by VVERA1 - CN /SET THE STEEL FOR THE FOOTER TRASH BIN.GOOD TO POUR .
|
| 09/27/2021 |
ENGR Grading Final |
MHERNANDEZ |
Continued |
Entered by NGARCIA3 - CN /CONTRACTOR RESCHEDULE FOR TOMORROW. |