Permit: DP21-0005
Permit Details
Apply Date:
01/08/2021
Applicant:
Miguel Noriega
Description:
SITE/GRADING - 1121 South 11th Avenue, New multi-family.
Permit Reviews
Permit Number - DP21-0005
Permit Status: Inspections
Permit Description: SITE/GRADING - 1121 South 11th Avenue, New multi-family.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/08/2021 | DEV PKG - OK TO SUBMIT | 01/14/2021 | COMPLETED |
| 01/14/2021 | DEV PKG | 02/25/2021 | COMPLETED |
| 08/30/2021 | DEV PKG - RESUBMITTAL | 10/25/2021 | COMPLETED |
| 10/28/2021 | DEV PKG - RESUBMITTAL | 11/30/2021 | COMPLETED |
Outstanding Inspections
Permit Status: Inspections
Permit Number: DP21-0005
Permite Description: SITE/GRADING - 1121 South 11th Avenue, New multi-family.
Total Outstanding Inspections - 17
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/26/2022 | COT - SITE - Zoning Intermediate | N/A | Not Ready | |
| 10/26/2022 | Final inspection to ensure all landscape and water harvesting SITE | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Correction Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Zoning Final | N/A | Not Ready | |
| 10/26/2022 | SITE | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/26/2022 | SITE - SWPPP Violation Notice | N/A | Not Ready | |
| 10/26/2022 | SITE - Zoning Compliance | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | COT - SIGN - Sign Electrical | N/A | Not Ready | |
| 10/26/2022 | COT - ENGR - Site - Assurance Release | N/A | Not Ready | |
| 10/26/2022 | COT - LCBU - CofO | N/A | Not Ready | |
| 10/26/2022 | COT - SIGN - Sign Footing and Excavation | N/A | Not Ready | |
| 10/26/2022 | COT - HCBU - CofO | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready | |
| 11/03/2025 | ENGR Engineering Final | N/A | Not Ready | No site work has been performed to date. |
Completed Inspections
Permit Status: Inspections
Permit Number: DP21-0005
Permit Description: SITE/GRADING - 1121 South 11th Avenue, New multi-family.
Total Completed Inspections - 5
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/15/2023 | PDSD Site/Engineering Division - Landscaping | Passed | ||
| 11/15/2023 | ENGR Grading Final | Passed | ||
| 11/15/2023 | SITE - Stormwater Setup and Controls | Passed | ||
| 11/15/2023 | COT - SIGN - Sign Final | Passed | ||
| 01/23/2025 | PDSD Engineering Division Pre-Construction SITE | Passed | Inform the contractor you need to call him inspections for stormwater follow up every two weeks and a place all the wattles along the fence line and the city is requiring density test |