Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Issued
Type:
Development Package
Apply Date:
09/25/2020
Applicant:
Kyle Shepherd
Description:
GRADING/SWPPP - La Estancia, Phase 2, Parcel 3.

Permit Reviews

Permit Number - DP20-0193
Permit Status: Issued
Permit Description: GRADING/SWPPP - La Estancia, Phase 2, Parcel 3.
Start Date Submittal Complete Date Status  
08/27/2020 DEV PKG - OK TO SUBMIT (GRADING ONLY) 09/28/2020 COMPLETED Review Details
09/28/2020 GRADING 11/25/2020 COMPLETED Review Details
12/10/2020 GRADING 01/26/2021 COMPLETED Review Details

Outstanding Activity Conditions

Permit Number - DP20-0193
Permit Status: Issued
Permit Description: GRADING/SWPPP - La Estancia, Phase 2, Parcel 3.
Total Outstanding Activity Conditions - 2
Date Name
07/14/2023 Separate submittal to PC RWRD is required for new connections to sewer, new water meters and upsized water meters. Contact sewer@pima.gov for review and assessment.
07/14/2023 Sewer condition must be accepted and released by Pima County prior to issuance of a Temporary Certificate of Occupancy.

Outstanding Inspections

Permit Status: Issued
Permit Number: DP20-0193
Permite Description: GRADING/SWPPP - La Estancia, Phase 2, Parcel 3.
Total Outstanding Inspections - 6
Last Inspection Date Description Inspector Results Comments
09/01/2023 SITE - Stormwater Setup and Controls N/A Complete (Recurring) multiple areas need wattle adjusted and staked off.
10/27/2023 SITE - Stormwater Final Inspection N/A Not Ready Ensure that all work is completed per the approved plans, and provide this department with the NOT Notice of Termination from the Arizona Department of Environment Quality for this Permit. What’s this information has been pre-AA inspection for this can be done and this portion of the permit can be approved.
09/29/2023 PDSD Site/Engineering Division - NPPO N/A Not Ready Complete all the work on this site as shown on the approved plans prior to calling in this inspection for a final
10/27/2023 ENGR Grading Final N/A Not Ready Complete this site as shown on the approved plans prior to calling this Inspection in again for another Grading Inspection.
04/25/2024 PDSD Site/Engineering Division - Landscaping N/A Partial Pass Partial inspection, I need to complete the landscaping per plan. Replace all dead plants and remove debris from basins.
01/05/2024 SITE - Stormwater Follow-up N/A Complete (Recurring) Minor cleanup of the sites under construction at this time, general clean of the streets and the basins will be required before the final approval once all work has been completed per the Approved plans.

Completed Inspections

Permit Status: Issued
Permit Number: DP20-0193
Permit Description: GRADING/SWPPP - La Estancia, Phase 2, Parcel 3.
Total Completed Inspections - 4
Date Description Inspector Results Comments
03/19/2021 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 03/19/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by VLEON1 - }
09/29/2023 SITE - Stormwater Setup and Controls Passed
10/27/2023 COT - ENGR - Signage Final Passed
10/27/2023 ENGR Engineering Final Passed

Documents

File Name Document Type  
REV-1_COT EXPLANATION LETTER 9.17.21, REVISION.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
PERMIT.PDF DOCUMENTS VIEW
1-22 OF 22.PDF DEVELOPMENT PACKAGE VIEW
COMMENT_RESPONSE_LETTER, 12.10.20.PDF DOCUMENTS VIEW
DRAINAGE REPORT_P1-P5.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GEOTECHNICAL_REPORT.PDF DOCUMENTS VIEW