Permit: DP20-0068
Permit Details
Apply Date:
04/03/2020
Applicant:
Edward Marley
Description:
SITE/GRADING - Jim Click Kia, service expansion. New building.
Permit Reviews
Permit Number - DP20-0068
Permit Status: Complete
Permit Description: SITE/GRADING - Jim Click Kia, service expansion. New building.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/02/2022 | DEV PKG - RESUBMITTAL | 04/04/2022 | COMPLETED |
04/01/2020 | DEV PKG | 04/30/2020 | COMPLETED |
04/03/2020 | DEV PKG - OK TO SUBMIT | 04/08/2020 | COMPLETED |
Outstanding Inspections
Permit Status: Complete
Permit Number: DP20-0068
Permite Description: SITE/GRADING - Jim Click Kia, service expansion. New building.
Total Outstanding Inspections - 7
Last Inspection Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/17/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Complete (Recurring) | {Activity date: 10/17/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN /INFORMED THE CONTRACTOR TO CALL IN EVERY TWO WEEKS .} |
01/30/2023 | PDSD Site/Engineering Division - NPPO | N/A | Complete (Recurring) | |
04/04/2023 | ENGR Engineering Final | N/A | Partial Pass | OK for TCO for a level four occupancy |
01/27/2023 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | |
03/06/2023 | ENGR Grading Final | N/A | Not Ready | The following items will still need to be addressed prior to closing this permit for the final. 1) Complete all work is shown on the approved plans or revise drawings for this site. 2) Redo the handicap parking signs for the The two handicap parking spaces, design bottoms on the post will need to be heightened, so that they are at least 7 feet above the existing grade currently in approximately 5 feet. 3) Install the long-term bicycle parking structure and shown on the approved plans west of the building south of the parking lot. |
01/30/2023 | SITE - Stormwater Final Inspection | N/A | Complete (Recurring) | |
01/27/2023 | SITE - Stormwater Setup and Controls | N/A | Complete (Recurring) |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0068
Permit Description: SITE/GRADING - Jim Click Kia, service expansion. New building.
Total Completed Inspections - 8
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
05/02/2023 | COT - ENGR - Signage Final | Passed | Extend height of van accessible sign to above 7 feet to bottom of sign. Damien with Concord construction at 308-0014. Please schedule all inspections associated with development package permit for final approval. | |
05/04/2023 | PDSD Site/Engineering Division - NPPO | Passed | ||
05/04/2023 | ENGR Engineering Final | Passed | ||
05/04/2023 | SITE - Stormwater Follow-up | Passed | ||
05/04/2023 | ENGR Grading Final | Passed | ||
05/04/2023 | SITE - Stormwater Final Inspection | Passed | ||
05/04/2023 | SITE - Stormwater Setup and Controls | Passed | ||
05/08/2023 | PDSD Site/Engineering Division - Landscaping | Passed |