Permit Details

Status:
Complete
Type:
Development Package
Address:
7211 S PARK AV
Address NEW:
7211 S PARK AV
Apply Date:
03/18/2020
Applicant:
Description:
GRADING / FLOODPLAIN - Pima Community College - install trench drain.

Permit Reviews

Permit Number - DP20-0061
Permit Status: Complete
Permit Description: GRADING / FLOODPLAIN - Pima Community College - install trench drain.
Start Date Submittal Complete Date Status  
02/13/2020 DEV PKG - OK TO SUBMIT 03/23/2020 COMPLETED Review Details
03/20/2020 DEV PKG 04/28/2020 COMPLETED Review Details
05/08/2020 DEV PKG - RESUBMITTAL 06/01/2020 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP20-0061
Permit Description: GRADING / FLOODPLAIN - Pima Community College - install trench drain.
Total Completed Inspections - 9
Date Description Inspector Results Comments
09/09/2022 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/18/2022; Status: Partial Approval; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - PARTIAL/ALL THE PLANTS ARE NOT PLANTED AND THE ROOF DRAIN NEED RIP RAP. OK FOR T.C.OF O.}
09/09/2022 PDSD Site/Engineering Division - NPPO Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
09/09/2022 ENGR Engineering Final Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
09/09/2022 SITE - Stormwater Follow-up Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 08/03/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN NO CHANGES AS OF TODAY.} ; {Activity date: 02/25/2022; Status: Continued; Inspector: DROBERTS; Comment: Entered by NGARCIA3 - CONTINUED, NO CONCERNS AT THIS TIME} ; {Activity date: 06/16/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CONTINUE/SETTING RCP}
09/09/2022 ENGR Grading Final Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
09/09/2022 SITE - Stormwater Final Inspection Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
09/09/2022 SITE - Stormwater Setup and Controls Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/06/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VVERA1 - CN} ; {Activity date: 03/14/2022; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by NGARCIA3 - CN / WORKING ON THE TRENCH DRAIN ON TH SOUTH EAST OF TH BUILDING .INFORMED THE CONTRACTOR THAT THEY NEED TO CLL IN INSPECTION EVERY TWO WEEKS} ; {Activity date: 05/12/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - } ; {Activity date: 05/11/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CN/ THERE IS TWO AREAS THAT ARE UNEVEN .THE ENGINEER IS COME OUT TO LOOK AT WITH JENSEN TO RESOLVE THE PROBLEM.}
09/09/2022 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 04/06/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CN INFORMED THE CONTRACTOR TO CALL EVERY TIME AS NEED TO INSPECT THE BACKFILL FOR THE NEW BOXS FOR DRAINAGE.}
09/09/2022 COT - ENGR - Signage Final Passed {Activity date: 09/09/2022; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }