Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
4206 N 1ST AV
Apply Date:
03/17/2020
Applicant:
Gene Goldstein
Description:
SITE - Rillito Crossings Market Place, parking lot, trash enclosure.

Permit Reviews

Permit Number - DP20-0058
Permit Status: Complete
Permit Description: SITE - Rillito Crossings Market Place, parking lot, trash enclosure.
Start Date Submittal Complete Date Status  
03/17/2020 DEV PKG - OK TO SUBMIT 03/20/2020 COMPLETED Review Details
03/19/2020 DEV PKG 04/28/2020 COMPLETED Review Details
05/14/2020 DEV PKG - RESUBMITTAL 06/17/2020 COMPLETED Review Details
07/09/2020 DEV PKG - RESUBMITTAL 08/05/2020 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP20-0058
Permit Description: SITE - Rillito Crossings Market Place, parking lot, trash enclosure.
Total Completed Inspections - 1
Date Description Inspector Results Comments
06/23/2021 ENGR Engineering Final Passed {Activity date: 06/23/2021; Status: Approved; Inspector: BBENEDON; Comment: Entered by VLEON1 - APPROVED FOR 4206 N 1ST AV - Approved. Please change permit status to final.} ; {Activity date: 05/26/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - NOT READY FOR 4206 N 1ST AV - CONSTRUCTION DEBRIS STILL REMAINS ON SITE} ; {Activity date: 03/02/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - NOT READY FOR 4206 N 1ST AVE CONSTRUCTION DEBRIS AND TEMPORARY TOILES REMAIN ON SITE} ; {Activity date: 02/05/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 4206 N 1ST AVE - Not ready

} ; {Activity date: 02/05/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - NOT READY FOR 4602 N 1ST AVE - BARRICADES, DEBRIS AND CONSTRUCTION EQUIPMENT STILL REMAIN ON SITE} ; {Activity date: 01/22/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - Not ready. Location of original enclosure has been repaired. New enclosure is still under construction. Construction debris remain on empty portion of lot} ; {Activity date: 01/08/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready} ; {Activity date: 01/08/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 01/08/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - } ; {Activity date: 01/08/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - FOR 4240 N 1ST AV - Not ready. Contractor grading area of demolition. Construction materials and debris and barricades on site.} ; {Activity date: 01/08/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - FOR 4206 N 1ST AV - Not ready. Contractor grading area of demolition. Construction materials and debris and barricades on site.

} ; {Activity date: 01/06/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - NR FOR 4280 N 1ST AV - Not ready. Inspection is for trash enclosure rebar for slab. And Ballard installation. OK for concrete. Leo at 661-7634.} ; {Activity date: 01/06/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - NR FOR 4240 N 1ST AV} ; {Activity date: 01/06/2021; Status: Not ready for Inspection; Inspector: TTREMBULAK; Comment: Entered by VLEON1 - NR FOR 4214 N 1ST AVE} ; {Activity date: 01/06/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by VLEON1 - Not ready. Inspection is for trash enclosure rebar for slab. And Ballard installation. OK for concrete. Leo at 661-7634.} ; {Activity date: 01/06/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09027. Not ready. Inspection is for trash enclosure rebar for slab. And Ballard installation. OK for concrete. Leo at 661-7634.

} ; {Activity date: 01/05/2021; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - 09027. Not ready. Inspection of trash enclosure slab and bollards.} ; {Activity date: 12/18/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Pre-grout inspection of new trash enclosure.
Temporary barricade fencing, debris and material piles and disturbed and stabilized dirt in various locations on site.Existing enclosure has been partially demolished. Track out is contained within private parking area.} ; {Activity date: 12/18/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Pre-grout inspection. Temporary barricade fencing, debris and material piles and disturbed and stabilized dirt in various locations on site.} ; {Activity date: 12/18/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready} ; {Activity date: 12/18/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Not ready. Leo is looking for a 1 PM pre-grout inspection and will contact Inspector as soon as work is ready.} ; {Activity date: 11/25/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. Trash enclosure footing OK} ; {Activity date: 11/25/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. Trash enclosure footing OK} ; {Activity date: 11/25/2020; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by PAHUMAD1 - Not ready. Inspection for enclosure footing. Leo 661-7634. Remote inspection. Insure that vertical rebar is installed at 32 inches on center.
Next inspection will be for pre-grout.

}

Documents

File Name Document Type  
1-6 OF 6.PDF DEVELOPMENT PACKAGE VIEW
PERMIT SIGNED - 8 5 20.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 07.09.20.PDF DOCUMENTS VIEW
COMMENT RESPONSE LETTER, 05.14.2020.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW