Permit: DP20-0029
Permit Details
Apply Date:
01/29/2020
Applicant:
Description:
GRADING - In-N-Out Burger, the Landing Shopping Center.
Permit Reviews
Permit Number - DP20-0029
Permit Status: Complete
Permit Description: GRADING - In-N-Out Burger, the Landing Shopping Center.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/31/2020 | GRADING | 02/27/2020 | COMPLETED |
03/17/2020 | DEV PKG - RESUBMITTAL | 03/20/2020 | COMPLETED |
12/30/2019 | DEV PKG - OK TO SUBMIT | 01/31/2020 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP20-0029
Permit Description: GRADING - In-N-Out Burger, the Landing Shopping Center.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/17/2020 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 07/17/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved} ; {Activity date: 04/02/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by SFLORES2 - Unscheduled, courtesy preconstruction meeting with Jose by telephone communication. Provide state of Arizona NOI. Post signage as required. Call for stormwater follow up inspections on a biweekly basis. Request inspections of all storm drain piping and drain box structures. Request inspections for all parking sign and Ballard footings. Trashing closure is for a compactor only.} |
|
07/21/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 07/21/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approve} | |
07/21/2020 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 07/21/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Approve} ; {Activity date: 04/02/2020; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by SFLORES2 - Controls installed along west and north perimeter’s. Track out grate installed. Concrete washout in place.} |
|
07/22/2020 | ENGR Grading Final | Passed | {Activity date: 07/22/2020; Status: Approved; Inspector: BBENEDON; Comment: Entered by JSCHNEI2 - Approved.} ; {Activity date: 04/09/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by DROBERT5 - OK FOR THE PLACEMENT OF CONCRETE FOR THE TRASH ENCLOSURE FOOTER} | |
07/27/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 07/27/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
07/27/2020 | ENGR Engineering Final | Passed | {Activity date: 07/27/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
07/27/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 07/27/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 06/10/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. No issues or concerns. Catch basins are protected} ; {Activity date: 05/18/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - No concerns at this time. } ; {Activity date: 04/02/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by VFLORES1 - NO ISSUES AT THIS TIME} ; {Activity date: 04/02/2020; Status: Continued; Inspector: BBENEDON; Comment: Entered by SFLORES2 - There are no issues or concerns at this time.} |
|
07/27/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 07/27/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
07/27/2020 | COT - ENGR - Signage Final | Passed | {Activity date: 07/27/2020; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |