Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 07/20/2020 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by JSCHNEI2 - Approved. Grading for asphalt |
| 07/16/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by JSCHNEI2 - Continued. Contractor preparing final grade for asphalt
|
| 06/25/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Pouring concrete at drive-through. Ab materials on site for final grading of asphalt areas. |
| 06/10/2020 |
ENGR Grading Final |
BBENEDON |
Partial Approval |
Entered by RSALDAT1 - Partially approved. Catch basins installed and protected. Contractor concentrating on building finish. Also landscaping and final grade repairing for asphalt.
|
| 06/09/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Preparing final grade for pavement. Jose with In-N-Out Burger |
| 05/27/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Preparing final grade |
| 05/18/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Contractors continuing work at main site entrance and drive-through. |
| 05/12/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Jose is in and out burger. Installing curbs and drive through. |
| 05/12/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - ontinued. Jose is in and out burger. Installing curbs and drive through. |
| 04/09/2020 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - OK FOR THE PLACEMENT OF BACKFILL FOR THE STORMWATER DRAINAGE SYSTEM, SEE THE PLANS FOR THE RUNS THAT HAVE BEEN APPROVED ON THIS DATE. |
| 04/02/2020 |
ENGR Grading Final |
RSALDATE |
Continued |
Entered by SFLORES2 - 12 inch storm drains east to west as well as from catch basin 35.6 invert, with sand bedding and cover.
|
| 04/02/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by SFLORES2 - 12 inch storm drains east to west as well as from catch basin 35.6 invert, with sand bedding and cover. |
| 07/21/2020 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approve |
| 07/21/2020 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by RSALDAT1 - Approve |
| 06/08/2020 |
ENGR Grading Final |
BBENEDON |
Continued |
Entered by RSALDAT1 - Continued. Grading and paving. Jose |
| 07/22/2020 |
ENGR Grading Final |
BBENEDON |
Approved |
Entered by JSCHNEI2 - Approved. |
| 04/09/2020 |
ENGR Grading Final |
RLEDONNE |
Partial Approval |
Entered by DROBERT5 - OK FOR THE PLACEMENT OF CONCRETE FOR THE TRASH ENCLOSURE FOOTER |