Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP20-0027
Permit Details
Apply Date:
01/27/2020
Applicant:
Description:
SITE/GRADING - El Rio Comm. Ctr, Congress Street project, minor parking lot addition.
Permit Reviews
Permit Number - DP20-0027
Permit Status: Issued
Permit Description: SITE/GRADING - El Rio Comm. Ctr, Congress Street project, minor parking lot addition.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/29/2020 | DEV PKG | 03/12/2020 | COMPLETED |
| 04/10/2020 | DEV PKG - RESUBMITTAL | 04/16/2020 | COMPLETED |
| 05/07/2020 | DEV PKG - OK TO SUBMIT | 06/09/2020 | COMPLETED |
| 06/09/2020 | REVISION - - 1ST | 07/17/2020 | COMPLETED |
| 12/26/2019 | DEV PKG - OK TO SUBMIT | 01/30/2020 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP20-0027
Permite Description: SITE/GRADING - El Rio Comm. Ctr, Congress Street project, minor parking lot addition.
Total Outstanding Inspections - 9
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/16/2021 | SITE - Stormwater Follow-up | N/A | Complete (Recurring) | {Activity date: 06/16/2021; Status: Continued; Inspector: MHERNANDEZ; Comment: Entered by VLEON1 - CONTINUE FOR 839 W CONGRESS ST} |
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready | |
| 10/27/2022 | ENGR Grading Final | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Setup and Controls | N/A | Not Ready | |
| 10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready |