Permit: DP19-0247
Permit Details
Apply Date:
10/08/2019
Applicant:
David Williamson
Description:
SITE/GRADING/ IID - Lester Warehouse.
Permit Reviews
Permit Number - DP19-0247
Permit Status: Issued
Permit Description: SITE/GRADING/ IID - Lester Warehouse.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/20/2021 | DEV PKG - RESUBMITTAL | 02/15/2021 | COMPLETED |
| 01/23/2020 | DEV PKG - RESUBMITTAL | 03/03/2020 | COMPLETED |
| 02/16/2021 | DEV PKG - RESUBMITTAL | 03/04/2021 | COMPLETED |
| 03/16/2021 | DEV PKG - RESUBMITTAL | 03/18/2021 | COMPLETED |
| 09/09/2019 | DEV PKG - OK TO SUBMIT | 10/11/2019 | COMPLETED |
| 10/11/2019 | DEV PKG | 11/13/2019 | COMPLETED |
| 03/06/2023 | DEVELOPMENT PACKAGE REVIEW v.2 | 05/11/2023 | APPROVED |
| 01/05/2023 | DEVELOPMENT PACKAGE REVIEW v.1 | 02/01/2023 | REQUIRES RESUBMIT |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP19-0247
Permite Description: SITE/GRADING/ IID - Lester Warehouse.
Total Outstanding Inspections - 2
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/19/2023 | ENGR Engineering Final | N/A | Not Ready | |
| 01/19/2023 | COT - ENGR - Signage Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: DP19-0247
Permit Description: SITE/GRADING/ IID - Lester Warehouse.
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/20/2023 | SITE - Stormwater Setup and Controls | Passed | N/A | |
| 01/20/2023 | SITE - Stormwater Final Inspection | Passed | ||
| 01/20/2023 | PDSD Site/Engineering Division - NPPO | Passed | N/A | |
| 01/20/2023 | PDSD Engineering Division Pre-Construction SITE | Passed | N/A | |
| 01/20/2023 | SITE - Stormwater Follow-up | Passed | N/A | |
| 01/20/2023 | PDSD Site/Engineering Division - Landscaping | Passed | N/A | |
| 02/03/2023 | ENGR Grading Final | Passed | ||
| 02/03/2023 | COT - ENGR - Signage Final | Passed |