Permit: DP19-0079
Permit Details
Apply Date:
04/02/2019
Applicant:
Brandy Burke
Description:
SITE/GRADING - Dutch Brothers, coffee shop with drive-thru.
Permit Reviews
Permit Number - DP19-0079
Permit Status: Complete
Permit Description: SITE/GRADING - Dutch Brothers, coffee shop with drive-thru.
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
02/19/2020 | DEV PKG - OK TO SUBMIT | 02/20/2020 | COMPLETED |
02/20/2020 | DEV PKG - REVISION | 02/21/2020 | COMPLETED |
03/01/2019 | DEV PKG - OK TO SUBMIT | 04/05/2019 | COMPLETED |
03/08/2019 | DEV PKG - OK TO SUBMIT | 04/15/2019 | COMPLETED |
04/15/2019 | DEV PKG | 05/09/2019 | COMPLETED |
07/19/2019 | DEV PKG - RESUBMITTAL | 08/20/2019 | COMPLETED |
08/29/2019 | DEV PKG - RESUBMITTAL | 09/03/2019 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP19-0079
Permit Description: SITE/GRADING - Dutch Brothers, coffee shop with drive-thru.
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/07/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/07/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Met with GC went over approved plans.} | |
02/06/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
02/06/2020 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
02/06/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 11/27/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by SFLORES2 - Track out is present on Park Avenue 36 street and on Martin Luther King Junior, however it is evident that it has been swept. Additionally two sweepers Are working the areas} | |
02/06/2020 | ENGR Grading Final | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
02/06/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
02/06/2020 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
02/06/2020 | COT - ENGR - Signage Final | Passed | {Activity date: 02/06/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
02/25/2020 | ENGR Engineering Final | Passed | {Activity date: 02/25/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 02/21/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Have approved revisions on site.Complete all striping of ADA parking area.} ; {Activity date: 02/13/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - engineering final notes apply to grading final.} ; {Activity date: 02/05/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - All notes pertaining to engineering final apply to grading final} |