Permit: DP19-0008
Permit Details
Status:
Complete
Type:
Development Package
Address:
9210 S HOUGHTON RD
Address NEW:
9210 S HOUGHTON RD
Apply Date:
01/14/2019
Applicant:
Description:
GRADING/SWPPP - Shops IV - Mod Pizza, Portions of lots 25-27.
Permit Reviews
Permit Number - DP19-0008
Permit Status: Complete
Permit Description: GRADING/SWPPP - Shops IV - Mod Pizza, Portions of lots 25-27.
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/14/2019 | DEV PKG - OK TO SUBMIT (GRADING ONLY) | 01/15/2019 | COMPLETED |
| 01/15/2019 | DEV PKG | 02/14/2019 | COMPLETED |
| 03/04/2019 | DEV PKG - RESUBMITTAL | 03/06/2019 | COMPLETED |
| 03/14/2019 | DEV PKG - RESUBMITTAL | 03/22/2019 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP19-0008
Permit Description: GRADING/SWPPP - Shops IV - Mod Pizza, Portions of lots 25-27.
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/29/2019 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 10/29/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Went over stormwater pollution prevention details with general contractor. He said he was going to put up and all Controls and NOI Info at gate this week.} | |
| 11/19/2019 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 11/19/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 11/19/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 11/19/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 11/19/2019 | COT - ENGR - Signage Final | Passed | {Activity date: 11/19/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } | |
| 03/18/2020 | SITE - Stormwater Follow-up | Passed | {Activity date: 03/18/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } ; {Activity date: 01/08/2020; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - GC canceled inspection.} ; {Activity date: 12/09/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 11/19/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - No concerns at this time.} ; {Activity date: 11/15/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Met with GC about calling in for storm water inspection’s.} | |
| 03/18/2020 | SITE - Stormwater Final Inspection | Passed | {Activity date: 03/18/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } | |
| 03/24/2020 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 03/24/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } ; {Activity date: 03/18/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Complete details from landscaping for staking trees} | |
| 04/15/2021 | ENGR Engineering Final | Passed | {Activity date: 04/15/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 03/24/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - } ; {Activity date: 03/18/2020; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by SFLORES2 - Sidewalks cross slope to trashing closure over 2%. Provide proper staking for landscaping for trees.} | |
| 04/15/2021 | ENGR Grading Final | Passed | {Activity date: 04/15/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |