Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
123 W DELANO ST
Apply Date:
01/08/2019
Applicant:
Description:
ELECTRIC GATE SITE

Permit Reviews

Permit Number - DP19-0002
Permit Status: Complete
Permit Description: ELECTRIC GATE SITE
Start Date Submittal Complete Date Status  
01/31/2019 SITE and/or GRADING 01/31/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP19-0002
Permit Description: ELECTRIC GATE SITE
Total Completed Inspections - 10
Date Description Inspector Results Comments
04/12/2019 COT - FCON - Fire - Final Passed {Activity date: 04/12/2019; Status: Approved; Inspector: jvincent; Comment: Entered by JVINCEN1 - }
05/02/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 04/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Provide city approved plans for inspection}
05/02/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 04/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Provide city approved plans for inspection}
05/02/2019 ENGR Engineering Final Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
05/02/2019 SITE - Stormwater Follow-up Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
05/02/2019 ENGR Grading Final Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 04/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Provide city approved plans for inspection}
05/02/2019 SITE - Stormwater Final Inspection Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
05/02/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - }
05/02/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 04/12/2019; Status: Denied; Inspector: BBENEDON; Comment: Entered by CBELL1 - Contractor did not show up for a scheduled meeting.}
05/02/2019 COT - ENGR - Signage Final Passed {Activity date: 05/02/2019; Status: Approved; Inspector: BBENEDON; Comment: Entered by CBELL1 - } ; {Activity date: 04/12/2019; Status: Not ready for Inspection; Inspector: BBENEDON; Comment: Entered by CBELL1 - Provide city approved plans for inspection}

Documents

File Name Document Type  
001_COVER SHEET_ 1.TIF DEVELOPMENT PACKAGE VIEW
002_ELECTRICAL_2.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW