Permit Number - DP18-0130
Permit Status: Complete
Permit Description: E SITE/GRADE/SWPPP - Raytheon Environmental Test Facility, Bldg. 930 (phase 1)
Start Date Submittal Complete Date Status  
05/31/2018 DEV PKG - OK TO SUBMIT 06/05/2018 COMPLETED Review Details
06/05/2018 DEV PKG 07/10/2018 COMPLETED Review Details
07/10/2018 DEV PKG - RESUBMITTAL 08/08/2018 COMPLETED Review Details
08/26/2019 REVISION - - 1ST 08/26/2019 COMPLETED Review Details
08/26/2019 DEV PKG - REVISION 09/18/2019 COMPLETED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP18-0130
Permite Description: E SITE/GRADE/SWPPP - Raytheon Environmental Test Facility, Bldg. 930 (phase 1)
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
12/05/2019 COT - RSEL - Outdoor Lighting N/A Canceled {Activity date: 12/05/2019; Status: Not Applicable; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - }

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0130
Permit Description: E SITE/GRADE/SWPPP - Raytheon Environmental Test Facility, Bldg. 930 (phase 1)
Total Completed Inspections - 10
Date Description Inspector Results Comments
08/08/2018 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 08/08/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SITE HAVE THE CONTROLS PLACED AROUND THE PERIMETER FENCE.}
08/09/2018 SITE - Stormwater Setup and Controls Passed {Activity date: 08/09/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETED ON 8/9/2018}
08/08/2019 ENGR Grading Final Passed {Activity date: 08/08/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - }
11/01/2019 COT - RSBU - Excavation/Rebar/Zoning Passed {Activity date: 11/01/2019; Status: Approved; Inspector: BSTEVENS; Comment: Entered by BSTEVENS - (RVI) LIGHT POLE BASES (8) OK TO POUR}
12/05/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 12/05/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/21/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor request temporary certificate of occupancy, engineering has no objection. Contractor is installing accessible ramp east of the building, landscaping around the building, ground coverings. And needs to complete the trash enclosure.
Unable to locate the superintendent or the approved civil plans.
Depress the landscape areas as shown on your approved plans.}
12/05/2019 COT - ENGR - Signage Final Passed {Activity date: 12/05/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - } ; {Activity date: 08/21/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor request temporary certificate of occupancy, engineering has no objection. Contractor is installing accessible ramp east of the building, landscaping around the building, ground coverings. And needs to complete the trash enclosure.
Unable to locate the superintendent or the approved civil plans.
Depress the landscape areas as shown on your approved plans.}
02/12/2020 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 02/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
02/12/2020 ENGR Engineering Final Passed {Activity date: 02/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/05/2019; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NEED ALL CLOSE OUT DOCUMENTATION FOR THIS PERMIT NOTICE OF TERMINATION, REVISED APPROVED DRAWINGS, CERTIFICATION LETTER FROM THE ENGINEER OF RECORD.

THERE ARE QUESTIONS IN REGARDS TO THE STANDING WATERS NOTED ON THIS SITE AT THIS TIME THAT ARE PAST THE 24 HOUR MAXIMUM DRAIN DOWN TIME. PROVIDE A CONTACT AND PHONE NUMBER TO BE UTILIZED IN SCHEDULING ALL FUTURE ANNUAL STORMWATER BASIN INSPECTIONS} ; {Activity date: 08/21/2019; Status: Partial Approval; Inspector: BBENEDON; Comment: Entered by DMERANZ1 - Contractor request temporary certificate of occupancy, engineering has no objection. Contractor is installing accessible ramp east of the building, landscaping around the building, ground coverings. And needs to complete the trash enclosure. Unable to locate the superintendent or the approved civil plans. Depress the landscape areas as shown on your approved plans.}
02/12/2020 SITE - Stormwater Follow-up Passed {Activity date: 02/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 06/10/2019; Status: Continued; Inspector: BBENEDON; Comment: Entered by CBELL1 - Minor check out noted on Merrill Park Boulevard.} ; {Activity date: 08/16/2018; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME.}
02/12/2020 SITE - Stormwater Final Inspection Passed {Activity date: 02/12/2020; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 12/05/2019; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - NEED NOTE FROM ADEQ}

Documents

File Name Document Type  
PERMIT.PDF DOCUMENTS VIEW
CONTRACTOR LETTER.PDF DOCUMENTS VIEW
APPLICATION.PDF DOCUMENTS VIEW
GEOTECH_REPORT.PDF DOCUMENTS VIEW
HYDRO_REPORT.PDF DOCUMENTS VIEW
RESPONSE LETTER.PDF DOCUMENTS VIEW
RESPONSE LETTER2.PDF DOCUMENTS VIEW
REVISION LETTER, 08.15.19.PDF DOCUMENTS VIEW
1-57 OF 57.PDF DEVELOPMENT PACKAGE VIEW