Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
9330 E GOLF LINKS RD
Apply Date:
03/15/2018
Applicant:
Description:
SITE/GRADING - DUTCH BROS COFFEE

Permit Reviews

Permit Number - DP18-0056
Permit Status: Complete
Permit Description: SITE/GRADING - DUTCH BROS COFFEE
Start Date Submittal Complete Date Status  
03/15/2018 DEV PKG - OK TO SUBMIT 03/15/2018 COMPLETED Review Details
03/15/2018 SITE and/or GRADING 04/23/2018 COMPLETED Review Details
05/02/2018 RESUB - SITE/GRADING ALL 06/06/2018 COMPLETED Review Details
05/13/2019 DEV PKG - REVISION 06/05/2019 COMPLETED Review Details
06/06/2018 RESUB - SITE and/or GRADING 04/26/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP18-0056
Permit Description: SITE/GRADING - DUTCH BROS COFFEE
Total Completed Inspections - 9
Date Description Inspector Results Comments
11/27/2018 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 11/27/2018; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - Met with GC and Grading contractor for pre-construction meeting went over Swift controls and trash and closures.}
01/25/2019 PDSD Site/Engineering Division - NPPO Passed {Activity date: 01/25/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by CBELL1 - }
05/16/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 05/16/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
05/16/2019 SITE - Stormwater Follow-up Passed {Activity date: 05/16/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/09/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - Walk site with GC no concerns at this time.} ; {Activity date: 02/25/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 02/20/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 02/13/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by CBELL1 - No concerns at this time} ; {Activity date: 02/05/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 01/31/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 01/28/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 01/04/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS.} ; {Activity date: 12/17/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 12/11/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.}
05/16/2019 ENGR Grading Final Passed {Activity date: 05/16/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
05/16/2019 SITE - Stormwater Final Inspection Passed {Activity date: 05/16/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/13/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by CBELL1 - }
05/16/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 05/16/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 11/30/2018; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WADDELS HAVE BEEN ADDED ON NORTH SIDE OF SITE.}
05/16/2019 COT - ENGR - Signage Final Passed {Activity date: 05/16/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
06/21/2019 ENGR Engineering Final Passed {Activity date: 06/21/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/16/2019; Status: Partial Approval; Inspector: MRAMBER; Comment: Entered by CBELL1 - See notes from engineering final.} ; {Activity date: 05/16/2019; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by CBELL1 - See notes from engineering final.}