Permit: DP17-0285
Permit Details
Status:
Issued
Type:
Development Package
Address:
4333 E SPEEDWAY BL
Address NEW:
4333 E SPEEDWAY BL
Apply Date:
11/30/2017
Applicant:
Description:
SITE - Royal Speedway dealership.1st Revision PENDING, March 2020 (sheets C1.0, P1.1, and P2.3).
Permit Reviews
Permit Number - DP17-0285
Permit Status: Issued
Permit Description: SITE - Royal Speedway dealership.1st Revision PENDING, March 2020 (sheets C1.0, P1.1, and P2.3).
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/10/2020 | DEV PKG - OK TO SUBMIT | 03/23/2020 | COMPLETED |
| 03/17/2020 | REVISION - - 1ST | 03/23/2020 | COMPLETED |
| 07/03/2018 | DEV PKG | 08/30/2018 | COMPLETED |
| 09/17/2018 | DEV PKG - RESUBMITTAL | 03/12/2020 | COMPLETED |
| 11/30/2017 | DEV PKG - OK TO SUBMIT | 11/30/2017 | COMPLETED |
| 11/30/2017 | DEV PKG | 01/16/2018 | COMPLETED |
Outstanding Inspections
Permit Status: Issued
Permit Number: DP17-0285
Permite Description: SITE - Royal Speedway dealership.1st Revision PENDING, March 2020 (sheets C1.0, P1.1, and P2.3).
Total Outstanding Inspections - 8
| Last Inspection Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/14/2021 | ENGR Grading Final | N/A | Complete (Recurring) | {Activity date: 07/14/2021; Status: Continued; Inspector: BBENEDON; Comment: Entered by RSALDAT1 - Continued. Expired permit. Corrections and completion of work required. TCO authorized by DR} |
| 10/26/2022 | PDSD Site/Engineering Division - NPPO | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Follow-up | N/A | Not Ready | |
| 10/26/2022 | SITE - Stormwater Final Inspection | N/A | Not Ready | |
| 10/26/2022 | PDSD Engineering Division Pre-Construction SITE | N/A | Not Ready | |
| 10/27/2022 | COT - ENGR - Signage Final | N/A | Not Ready | |
| 10/27/2022 | PDSD Site/Engineering Division - Landscaping | N/A | Not Ready | |
| 10/27/2022 | ENGR Engineering Final | N/A | Not Ready |
Completed Inspections
Permit Status: Issued
Permit Number: DP17-0285
Permit Description: SITE - Royal Speedway dealership.1st Revision PENDING, March 2020 (sheets C1.0, P1.1, and P2.3).
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/08/2019 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 11/08/2019; Status: Approved; Inspector: DROBERTS; Comment: Entered by DMERANZ1 - } |