Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
4646 E 22ND ST
Apply Date:
11/08/2017
Applicant:
Michael John Baker
Description:
CAR DEALERSHIP

Permit Reviews

Permit Number - DP17-0265
Permit Status: Complete
Permit Description: CAR DEALERSHIP
Start Date Submittal Complete Date Status  
01/05/2018 RESUB - SITE/GRADING ALL 02/07/2018 COMPLETED Review Details
02/07/2018 RESUB - SITE and/or GRADING 03/16/2018 COMPLETED Review Details
11/08/2017 DEV PKG - OK TO SUBMIT 11/08/2017 COMPLETED Review Details
11/08/2017 SITE and/or GRADING 12/12/2017 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP17-0265
Permit Description: CAR DEALERSHIP
Total Completed Inspections - 9
Date Description Inspector Results Comments
12/13/2018 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 PDSD Site/Engineering Division - NPPO Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 ENGR Engineering Final Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 SITE - Stormwater Follow-up Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 05/17/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 05/08/2018; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO CONCERNS AT THIS TIME, THE CREWS ARE WORKING ON THE INSTALLATION OF THE 24 INCH STORMDRAIN PIPES.}
12/13/2018 ENGR Grading Final Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 SITE - Stormwater Final Inspection Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 SITE - Stormwater Setup and Controls Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
12/13/2018 COT - ENGR - Signage Final Passed {Activity date: 12/13/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }

Documents

File Name Document Type  
001_1 OF 3.TIF DEVELOPMENT PACKAGE VIEW
002_2 OF 3.TIF DEVELOPMENT PACKAGE VIEW
003_3 OF 3.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW