Permit: DP16-0235
Permit Details
Apply Date:
12/27/2016
Applicant:
Lisa Bowers
Description:
demo & new restaurant/retail
Permit Reviews
Permit Number - DP16-0235
Permit Status: Complete
Permit Description: demo & new restaurant/retail
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/07/2017 | RESUB - SITE and/or GRADING | 03/30/2017 | COMPLETED |
| 03/30/2017 | RESUB - SITE and/or GRADING | 06/20/2017 | COMPLETED |
| 06/20/2017 | REVISION - SITE | 07/10/2017 | COMPLETED |
| 12/27/2016 | DEV PKG - OK TO SUBMIT | 12/27/2016 | COMPLETED |
| 12/27/2016 | SITE and/or GRADING | 02/07/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0235
Permit Description: demo & new restaurant/retail
Total Completed Inspections - 8
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/20/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 09/20/2017; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) SITE IS LESS THAN 1 ACRE THEREFORE NO SWPPP IS REQUIRED, HOWEVER THE CONTRACTOR MUST KEEP DISTURBED SOIL ON SITE DURING CONSTRUCTION. 2) LOOKED AT RE-BAR AND FOOTINGS FOR TRASH ENCLOSURES - OK FOR CONCRETE 3) CALL FOR RE-INSPECTION FOR TRASH ENCLOSURE PAD AND APRON. 4) CALL FOR INSPECTION FOR ANY SITE/GRADING/LANDSCAPE CONCERNS} |
|
| 02/07/2018 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 02/07/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/07/2018 | SITE - Stormwater Follow-up | Passed | {Activity date: 02/07/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 01/08/2018; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 12/19/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} ; {Activity date: 10/17/2017; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME} | |
| 02/07/2018 | SITE - Stormwater Final Inspection | Passed | {Activity date: 02/07/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - FILE A NOTICE OF TERMINATION WITH ADEQ} | |
| 02/07/2018 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 02/07/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/07/2018 | COT - ENGR - Signage Final | Passed | {Activity date: 02/07/2018; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 02/12/2018 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 02/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 03/18/2021 | ENGR Engineering Final | Passed | {Activity date: 03/18/2021; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/16/2018; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/12/2018; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 02/07/2018; Status: Partial Approval; Inspector: MRUSSO; Comment: Entered by DROBERT5 - 1) BLDG PERMIT FOR ENGINEERING HAS BEEN APPROVED. 2) AWATING A CERTIFICATION STATEMENT FROM THE EOR FOR FINAL GRADING APPROVAL} |