Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
06/02/2016
Applicant:
Lisa Bowers
Description:
SITE/GRADE POPEYE'S RESTAURANTOriginal approval 3/7/17 (1-10)1st revision approved 8/4/17 (1-4

Permit Reviews

Permit Number - DP16-0094
Permit Status: Complete
Permit Description: SITE/GRADE POPEYE'S RESTAURANTOriginal approval 3/7/17 (1-10)1st revision approved 8/4/17 (1-4
Start Date Submittal Complete Date Status  
03/03/2017 DEV PKG - RESUBMITTAL 07/14/2017 COMPLETED Review Details
06/02/2016 DEV PKG - OK TO SUBMIT 06/14/2016 COMPLETED Review Details
06/14/2016 DEV PKG 10/04/2016 COMPLETED Review Details
07/14/2017 DEV PKG - REVISION 08/07/2017 COMPLETED Review Details
10/04/2016 DEV PKG - RESUBMITTAL 11/08/2016 COMPLETED Review Details
11/08/2016 DEV PKG - RESUBMITTAL 03/03/2017 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP16-0094
Permit Description: SITE/GRADE POPEYE'S RESTAURANTOriginal approval 3/7/17 (1-10)1st revision approved 8/4/17 (1-4
Total Completed Inspections - 9
Date Description Inspector Results Comments
07/10/2017 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 07/10/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/07/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH GC WENT OVER WORK TO COMPLTE BEFORE STARTING GRADING WORK.}
10/23/2017 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/23/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/31/2017 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/31/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/31/2017 SITE - Stormwater Follow-up Passed {Activity date: 10/31/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 10/11/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/29/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 08/14/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH GC ABOUT TRACK OUT CLEANING STREET.} ; {Activity date: 08/08/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS .} ; {Activity date: 07/26/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.}
10/31/2017 ENGR Grading Final Passed {Activity date: 10/31/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/31/2017 SITE - Stormwater Final Inspection Passed {Activity date: 10/31/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/31/2017 SITE - Stormwater Setup and Controls Passed {Activity date: 10/31/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/31/2017 COT - ENGR - Signage Final Passed {Activity date: 10/31/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 10/27/2017; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
11/03/2017 ENGR Engineering Final Passed {Activity date: 11/03/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 10/31/2017; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NOTE UNDER ENGINEERING.}