Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Permit Details

Status:
Complete
Type:
Development Package
Address:
801 E 12TH ST
Address NEW:
801 E 12TH ST
Apply Date:
04/25/2016
Applicant:
Description:
SITE/GRADING/SWPPP - NEW BUS TERMINAL AND PARKING

Permit Reviews

Permit Number - DP16-0071
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - NEW BUS TERMINAL AND PARKING
Start Date Submittal Complete Date Status  
04/25/2016 DEV PKG - OK TO SUBMIT 04/25/2016 COMPLETED Review Details
04/25/2016 SITE and/or GRADING 05/24/2016 COMPLETED Review Details
05/26/2016 RESUB - SITE and/or GRADING 06/28/2016 COMPLETED Review Details
06/28/2016 RESUB - SITE and/or GRADING 07/07/2016 COMPLETED Review Details
07/07/2016 RESUB - SITE and/or GRADING 08/23/2016 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP16-0071
Permit Description: SITE/GRADING/SWPPP - NEW BUS TERMINAL AND PARKING
Total Completed Inspections - 9
Date Description Inspector Results Comments
08/30/2016 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 08/30/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH GC . CLEAN STREETS OF TRACK OUT.}
01/19/2017 PDSD Site/Engineering Division - NPPO Passed {Activity date: 01/19/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
01/19/2017 SITE - Stormwater Follow-up Passed {Activity date: 01/19/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 12/23/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS.} ; {Activity date: 12/07/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 11/09/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 10/18/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS ATTHIS TIME.} ; {Activity date: 09/28/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH GC ABOUT PROVIDING WASH OUT.}
01/19/2017 SITE - Stormwater Final Inspection Passed {Activity date: 01/19/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
01/19/2017 SITE - Stormwater Setup and Controls Passed {Activity date: 01/19/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
03/09/2017 COT - ENGR - Signage Final Passed {Activity date: 03/09/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
03/23/2017 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 03/23/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by KROBLES1 - }
03/23/2017 ENGR Engineering Final Passed {Activity date: 03/23/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by KROBLES1 - } ; {Activity date: 03/10/2017; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE CERT LETTER FOR ALL DRAINAGE AND GRADING FROM ENGINEER OF RECORD. COMPLET ALL ROOF DRAINS. FASTEN ADA PARKING SIGNS TO BUILDING. COMPLET ALL LANDSCAPING ON SITE.} ; {Activity date: 03/09/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - REMOVE ALL CONSTRUCTION EQUIPMENT FROM PARKING AREAS. INSTALL BIKE PARKING. PROVIDE COT AP CHANGES FOR BUS PARKING AREAS. REMOVE TEMP FENCEING AROUND SITE. REMOVE ALL TRASH FROM SITE.}
03/23/2017 ENGR Grading Final Passed {Activity date: 03/23/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by KROBLES1 - }