Permit: DP16-0061
Permit Details
Apply Date:
04/07/2016
Applicant:
David Shambach
Description:
ADDITION RENOVATION ALPAHPHI
Permit Reviews
Permit Number - DP16-0061
Permit Status: Complete
Permit Description: ADDITION RENOVATION ALPAHPHI
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/28/2017 | REVISION - SITE | 02/28/2017 | COMPLETED |
| 04/07/2016 | SITE and/or GRADING | 12/21/2016 | COMPLETED |
| 09/26/2017 | REVISION - SITE | 09/26/2017 | COMPLETED |
| 12/21/2016 | REVISION - SITE | 02/28/2017 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0061
Permit Description: ADDITION RENOVATION ALPAHPHI
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/29/2017 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | ENGR Engineering Final | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | SITE - Stormwater Follow-up | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | ENGR Grading Final | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | SITE - Stormwater Final Inspection | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } | |
| 09/29/2017 | COT - ENGR - Signage Final | Passed | {Activity date: 09/29/2017; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } |