Permit Details

Status:
Complete
Type:
Development Package
Apply Date:
01/22/2016
Applicant:
Lisa Bowers
Description:
SITE/GRADING

Permit Reviews

Permit Number - DP16-0015
Permit Status: Complete
Permit Description: SITE/GRADING
Start Date Submittal Complete Date Status  
01/22/2016 DEV PKG - OK TO SUBMIT 01/22/2016 COMPLETED Review Details
01/22/2016 SITE and/or GRADING 03/04/2016 COMPLETED Review Details
03/04/2016 RESUB - SITE and/or GRADING 03/09/2016 COMPLETED Review Details
03/09/2016 RESUB - SITE and/or GRADING 03/22/2016 COMPLETED Review Details
03/22/2016 RESUB - SITE and/or GRADING 03/30/2016 ACTIVE Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP16-0015
Permit Description: SITE/GRADING
Total Completed Inspections - 9
Date Description Inspector Results Comments
04/08/2016 SITE - Stormwater Setup and Controls Passed {Activity date: 04/08/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/07/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/08/2016 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 04/08/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/07/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/01/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH DALE NO AP PLANS OR PERMITS ON SITE.}
10/03/2016 PDSD Site/Engineering Division - NPPO Passed {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/03/2016 SITE - Stormwater Follow-up Passed {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/28/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 07/07/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WALKED SITE WITH GC . WENT OVER CLEAN UP TO SWPPP CONTROLS.}
10/03/2016 SITE - Stormwater Final Inspection Passed {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/03/2016 COT - ENGR - Signage Final Passed {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/24/2016 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 10/24/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
10/24/2016 ENGR Engineering Final Passed {Activity date: 10/24/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 10/03/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET ALL WORK ON AP PLANS. PROVIDE STBILIZATION TO ALL DISTURBED AREAS DURING CONSTRUCTION . PROVIDE RAIL AT BOTTOM OF ADA RAMP.}
10/24/2016 ENGR Grading Final Passed {Activity date: 10/24/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }