Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP16-0015
Permit Details
Apply Date:
01/22/2016
Applicant:
Lisa Bowers
Description:
SITE/GRADING
Permit Reviews
Permit Number - DP16-0015
Permit Status: Complete
Permit Description: SITE/GRADING
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/22/2016 | DEV PKG - OK TO SUBMIT | 01/22/2016 | COMPLETED |
01/22/2016 | SITE and/or GRADING | 03/04/2016 | COMPLETED |
03/04/2016 | RESUB - SITE and/or GRADING | 03/09/2016 | COMPLETED |
03/09/2016 | RESUB - SITE and/or GRADING | 03/22/2016 | COMPLETED |
03/22/2016 | RESUB - SITE and/or GRADING | 03/30/2016 | ACTIVE |
Completed Inspections
Permit Status: Complete
Permit Number: DP16-0015
Permit Description: SITE/GRADING
Total Completed Inspections - 9
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/08/2016 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 04/08/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/07/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
04/08/2016 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 04/08/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/07/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/01/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH DALE NO AP PLANS OR PERMITS ON SITE.} | |
10/03/2016 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
10/03/2016 | SITE - Stormwater Follow-up | Passed | {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 07/28/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 07/07/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WALKED SITE WITH GC . WENT OVER CLEAN UP TO SWPPP CONTROLS.} | |
10/03/2016 | SITE - Stormwater Final Inspection | Passed | {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
10/03/2016 | COT - ENGR - Signage Final | Passed | {Activity date: 10/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
10/24/2016 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 10/24/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
10/24/2016 | ENGR Engineering Final | Passed | {Activity date: 10/24/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 10/03/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET ALL WORK ON AP PLANS. PROVIDE STBILIZATION TO ALL DISTURBED AREAS DURING CONSTRUCTION . PROVIDE RAIL AT BOTTOM OF ADA RAMP.} | |
10/24/2016 | ENGR Grading Final | Passed | {Activity date: 10/24/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } |