Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP15-0214
Permit Details
Status:
Complete
Type:
Development Package
Address:
7130 S NOGALES HY
Address NEW:
7130 S NOGALES HY
Apply Date:
12/09/2015
Applicant:
Description:
SITE - EL MESQUITEREVISION 1 APPROVED ON 02/09/2017 (SHEET 1, 2, 3)
Permit Reviews
Permit Number - DP15-0214
Permit Status: Complete
Permit Description: SITE - EL MESQUITEREVISION 1 APPROVED ON 02/09/2017 (SHEET 1, 2, 3)
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 02/05/2016 | RESUB - SITE/GRADING ALL | 03/07/2016 | COMPLETED |
| 02/09/2017 | REVISION - - 1ST | 02/09/2017 | COMPLETED |
| 03/08/2016 | RESUB - SITE and/or GRADING | 03/18/2016 | COMPLETED |
| 04/20/2017 | REVISION - SITE | 04/20/2017 | COMPLETED |
| 12/09/2015 | DEV PKG - OK TO SUBMIT | 12/09/2015 | COMPLETED |
| 12/09/2015 | SITE and/or GRADING | 01/08/2016 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP15-0214
Permit Description: SITE - EL MESQUITEREVISION 1 APPROVED ON 02/09/2017 (SHEET 1, 2, 3)
Total Completed Inspections - 2
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/18/2017 | SITE - Zoning Final | Passed | {Activity date: 10/18/2017; Status: Approved; Inspector: RDLD; Comment: Entered by KROBLES1 - } ; {Activity date: 05/04/2016; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - CREWS STILL WORKING ON THE COMBO PERMIT AT THIS TIME.} ; {Activity date: 04/14/2016; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NOTHING FOR THIS SITE HAS BEEN COMPLETED AT THIS TIME.I WILL CONTINUE TO CHECK THIS SITE AND WILL MAKE CHANGES TO THESE INSPECTIONS AS NEEDED.} | |
| 10/18/2017 | ENGR Engineering Final | Passed | {Activity date: 10/18/2017; Status: Approved; Inspector: RDLD; Comment: Entered by KROBLES1 - } ; {Activity date: 02/24/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET ON SITE ABOUT ADA PARKING.} ; {Activity date: 05/04/2016; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NOTHING READY ON THE SITE AT THIS TIME.} ; {Activity date: 04/18/2016; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - CHECKED ON THE SITE AS I WENT INTO WORK TO SEE IF THE ROWS OF BLOCKS HAD BEEN INSTALLED OVER THE WEEKEND. THE SITE IS STILL IN THE SAME CONDITION AS I LEFT IT ON FRIDAY 15TH. NOTHING HAS BEEN SCHEDULED IN THE INSPECTIONS FOR THIS SITE FOR TODAY.} ; {Activity date: 04/15/2016; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - I STOPPED BY IN THE MORNING TOSS MEET WITH THE CONTRACTOR AND DISCUSS WHAT HIS INTENTIONS ARE FOR TODAY. THEY HAVE MARKED THE CELLS THAT HAVE REBAR IN THEM, THREE OF THE CELLS HAVE BEEN MARKED BUT THEY HAVE MISSED THE INSTALLATION OF THE BARS DURING THE GROUTING PROCESS. THESE BARS WILL BE DRILLED IN AND EPOXIED PRIOR TO CONTINUING THE CONSTRUCTION ON THE REST OF THE WALL. I WILL CHECK THIS SITE AT THE END OF THE DAY AND SEE HOW THE WORKED HAS PROGRESSED. LOOKED AT THE SITE AT THE END OF THE DAY, THEY ARE MISSING 3 COURSES TO COMPLETE TO THE NEXT BOND BEAM. THIS WORK WILL BE DONE OVER THE WEEKEND AND SHOULD BE READY FOR GROUT ON MONDAY. THE CONTRACTOR HAS ASKED ABOUT THE LENTLE THAT IS TO GO OVER THE DOORWAY INTO THE STRUCTURE. I HAVE ADVISED HIM TO CONTACT THE ENGINEER OF RECORD TO SEE WHAT IS HIS REQUIREMENTS PER THIS APPROVED PLAN.} ; {Activity date: 04/14/2016; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - LOOKED AT THE CONSTRUCTION OF THE NEW WALLS FOR THE ADDITION AT THE SOUTHEAST CORNER OF THE BUILDING. THE CREW HAS CONSTRUCTED THE FIRST 4 FEET LIFT AND IS APPROVED FOR GROUT. I CHECKED THE SITE IN THE AFTERNOON TO VERIFY THAT THEY HAD COMPLETED THE GROUT AND ARE READY FOR A 2ND LIFT.} |