Permit: DP15-0131
Permit Details
Status:
Complete
Type:
Development Package
Address:
3526 E FORT LOWELL RD
Address NEW:
3526 E FORT LOWELL RD
Apply Date:
08/11/2015
Applicant:
Lisa Bowers
Description:
SITE; AGM COMMERICAL BUILDINGOriginally approved 11/5/2015
Permit Reviews
Permit Number - DP15-0131
Permit Status: Complete
Permit Description: SITE; AGM COMMERICAL BUILDINGOriginally approved 11/5/2015
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 08/11/2015 | DEV PKG - OK TO SUBMIT | 08/11/2015 | COMPLETED |
| 08/11/2015 | DEV PKG | 09/30/2015 | COMPLETED |
| 09/30/2015 | DEV PKG - RESUBMITTAL | 11/10/2015 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP15-0131
Permit Description: SITE; AGM COMMERICAL BUILDINGOriginally approved 11/5/2015
Total Completed Inspections - 9
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/29/2016 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | PDSD Site/Engineering Division - NPPO | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | ENGR Engineering Final | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | SITE - Stormwater Follow-up | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | ENGR Grading Final | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | SITE - Stormwater Final Inspection | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } | |
| 06/29/2016 | COT - ENGR - Signage Final | Passed | {Activity date: 06/29/2016; Status: Approved; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - } |