Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Permit Details

Status:
Complete
Type:
Development Package
Address:
2051 N 13TH AV
Address NEW:
2051 N 13TH AV
Apply Date:
01/26/2015
Applicant:
Steven Shell
Description:
SITE/GRADING: TI - LOOMIS ARMORED

Permit Reviews

Permit Number - DP15-0009
Permit Status: Complete
Permit Description: SITE/GRADING: TI - LOOMIS ARMORED
Start Date Submittal Complete Date Status  
01/26/2015 DEV PKG - OK TO SUBMIT (GRADING ONLY) 01/26/2015 COMPLETED Review Details
02/10/2015 SITE and/or GRADING 03/17/2015 COMPLETED Review Details
02/12/2016 REVISION - SITE 02/18/2016 COMPLETED Review Details
03/17/2015 RESUB - SITE and/or GRADING 11/13/2015 COMPLETED Review Details
11/17/2015 REVISION - - 1ST 11/19/2015 COMPLETED Review Details

Outstanding Inspections

Permit Status: Complete
Permit Number: DP15-0009
Permite Description: SITE/GRADING: TI - LOOMIS ARMORED
Total Outstanding Inspections - 1
Last Inspection Date Description Inspector Results Comments
11/18/2015 SITE - Stormwater Final Inspection N/A Partial Pass {Activity date: 11/18/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 11/18/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE SITE FULLY PRIOR TO CALLING IN FOR THIS INSPECTION.}

Completed Inspections

Permit Status: Complete
Permit Number: DP15-0009
Permit Description: SITE/GRADING: TI - LOOMIS ARMORED
Total Completed Inspections - 6
Date Description Inspector Results Comments
11/18/2015 SITE - Stormwater Follow-up Passed {Activity date: 11/18/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
11/18/2015 ENGR Grading Final Passed {Activity date: 11/18/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
11/18/2015 SITE - Stormwater Setup and Controls Passed {Activity date: 11/18/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
11/18/2015 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 11/18/2015; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - }
01/29/2016 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 01/29/2016; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - THIS SITE IS BEING APPROVED PER THE E-MAIL FROM RUSSLYN WELLS TO GLENN MOYER AND ANDREW CONNOR DATED 12/17/*2015 AT 4:41 p.m. WHICH HAS BEEN POSTED BELOW:

>>> Russlyn Wells 12/17/2015 4:41 PM >>>

Glenn,

The original set of approved plans included a landscape plan but that drawing/plan was not approved/stamped and the landscaping was never installed.

The Loomis use was not considered to be a change of use and so there was no need to bring the site into compliance. Since the original landscape plan was not approved there is no need to "go back" to that plan.

Russ} ; {Activity date: 12/04/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - SEE PREVIOUS COMMENTS, INSTALL THE PLANTS ON THIS SITE AS PREVIOUSLY NOTED ON THE LAST APPROVED SITE PLAN. NO LANDSCAPING WAS REQUIRED FOR THIS SITE UNDER THE CURRENT PLANS} ; {Activity date: 11/18/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE THE SITE AS SHOWN ON THE APPROVED PLAN PRIOR TO CALLING IN FOR THE FINAL. THIS SITE IS OKAY FOR A TEMPORARY C OF O BUT NOT FOR THE FINAL APPROVAL. THE CONTRACTOR IS AWARE OF THE SIDEWALK AND HANDICAP ACCESS ITEMS THAT NEED TO BE ADDRESSED PRIOR TO THE FINAL APPROVAL.}
02/23/2016 ENGR Engineering Final Passed {Activity date: 02/23/2016; Status: Approved; Inspector: DROBERTS; Comment: Entered by DROBERT5 - } ; {Activity date: 12/14/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE THE SITE AS SHOWN ON THE APPROVED PLAN PRIOR TO CALLING IN FOR THE FINAL. THIS SITE IS OKAY FOR A TEMPORARY C OF O BUT NOT FOR THE FINAL APPROVAL. THE CONTRACTOR IS AWARE OF THE SIDEWALK AND HANDICAP ACCESS ITEMS THAT NEED TO BE ADDRESSED PRIOR TO THE FINAL APPROVAL.} ; {Activity date: 11/18/2015; Status: Partial Approval; Inspector: DROBERTS; Comment: Entered by DROBERT5 - COMPLETE THE SITE AS SHOWN ON THE APPROVED PLAN PRIOR TO CALLING IN FOR THE FINAL. THIS SITE IS OKAY FOR A TEMPORARY C OF O BUT NOT FOR THE FINAL APPROVAL. THE CONTRACTOR IS AWARE OF THE SIDEWALK AND HANDICAP ACCESS ITEMS THAT NEED TO BE ADDRESSED PRIOR TO THE FINAL APPROVAL. PROVIDE THE REVISED AS-BUILT DRAWINGS AND A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD.}

Documents

File Name Document Type  
001_COVER SHEET_DP-1.TIF DEVELOPMENT PACKAGE VIEW
002_SITE DEMOLITION_DP-2.TIF DEVELOPMENT PACKAGE VIEW
003_SITE_DP-3.TIF DEVELOPMENT PACKAGE VIEW
004_SITE DETAILS_DP-4.TIF DEVELOPMENT PACKAGE VIEW
005_NOTES_DP-5.TIF DEVELOPMENT PACKAGE VIEW
006_GRADING / PAVING_DP-6.TIF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW