Permit: DP14-0151
Permit Details
Apply Date:
09/04/2014
Applicant:
Description:
SITE - OFFICE
Permit Reviews
Permit Number - DP14-0151
Permit Status: Complete
Permit Description: SITE - OFFICE
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/23/2015 | RESUB - SITE and/or GRADING | 05/29/2015 | COMPLETED |
| 02/04/2016 | REVISION - SITE | 02/18/2016 | COMPLETED |
| 05/29/2015 | REVISION - SITE | 07/21/2015 | COMPLETED |
| 07/21/2015 | REVISION - SITE | 07/23/2015 | COMPLETED |
| 09/04/2014 | DEV PKG - OK TO SUBMIT | 09/18/2014 | COMPLETED |
| 09/22/2014 | SITE and/or GRADING | 10/24/2014 | COMPLETED |
| 11/24/2015 | REVISION - SITE | 02/04/2016 | COMPLETED |
| 12/22/2014 | SITE and/or GRADING | 12/23/2014 | COMPLETED |
| 12/23/2014 | RESUB - SITE and/or GRADING | 01/23/2015 | COMPLETED |
Outstanding Activity Conditions
Permit Number - DP14-0151
Permit Status: Complete
Permit Description: SITE - OFFICE
Total Outstanding Activity Conditions - 1
| Date | Name |
|---|---|
| 01/23/2015 | Security barrier required completely around the basin. |
Completed Inspections
Permit Status: Complete
Permit Number: DP14-0151
Permit Description: SITE - OFFICE
Total Completed Inspections - 1
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/03/2016 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 08/03/2016; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 08/01/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - INSTALL PER SITE KEY NTES ON PAGE DP1.} ; {Activity date: 07/28/2016; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } |