Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Permit: DP14-0013
Permit Details
Apply Date:
01/30/2014
Applicant:
Description:
SITE PLAN - DOWNTOWN MOTOR APARTMENTSOriginally approved 11/5/20141st Revision approved 9/24/2
Permit Reviews
Permit Number - DP14-0013
Permit Status: Complete
Permit Description: SITE PLAN - DOWNTOWN MOTOR APARTMENTSOriginally approved 11/5/20141st Revision approved 9/24/2
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/30/2014 | DEV PKG - OK TO SUBMIT | 01/30/2014 | COMPLETED |
01/30/2014 | SITE and/or GRADING | 02/12/2014 | COMPLETED |
02/14/2017 | DEV PKG - REVISION | 03/08/2017 | COMPLETED |
02/25/2014 | SITE and/or GRADING | 02/27/2014 | COMPLETED |
07/21/2015 | DEV PKG - REVISION | 08/25/2015 | COMPLETED |
08/25/2015 | DEV PKG - REVISION | 09/10/2015 | COMPLETED |
09/24/2015 | DEV PKG - REVISION | 02/14/2017 | COMPLETED |
10/29/2014 | DEV PKG - RESUBMITTAL | 11/03/2014 | COMPLETED |
11/03/2014 | DEV PKG - RESUBMITTAL | 07/20/2015 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP14-0013
Permit Description: SITE PLAN - DOWNTOWN MOTOR APARTMENTSOriginally approved 11/5/20141st Revision approved 9/24/2
Total Completed Inspections - 1
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/13/2017 | ENGR Engineering Final | Passed | {Activity date: 03/13/2017; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/27/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - LOOED OVER THE AREA TO SEE WHAT WORK THEY WERE CALLING IN FOR APPROVAL. THE CONTRACTOR IS PLACING THE REBAR AND THE EXPANSION JOINT MATERIAL FOR THE POURING OF THE FLOOR AND THE ADJACENT SIDEWALK. THEY HAVE SCHEDULED THIS POUR FOR TOMORROW MORNING WEATHER PERMITTING, IT WILL BE POURED ON WEDNESDAY IF IT IS TO WET TOMORROW. THEY HAVE ADVISED ME THAT THE GATES MAY GET INSTALLED THE EARLY PART OF NEXT WEEK AND SHOULD BE CALLING IN FOR THE FINAL AT THAT TIME.} ; {Activity date: 02/22/2017; Status: Continued; Inspector: DROBERTS; Comment: Entered by DROBERT5 - LOOKED AT THE RESEEDING OF THE PROPERTY SOUTH OF THIS SITE, ALL APPEARS TO BE GOOD AT THIS TIME. THE REMAINING ITEM FOR THIS SITE IS THE TRASH ENCLOSURE CONSTRUCTION, POURING OF THE FLOORS, SIDEWALKS, AND INSTALLATION OF THE GATES FOR EACH ENCLOSURE.} ; {Activity date: 01/11/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET GC ON SITE ABOUT CURB ON NORTH EAST SIDE OF SITE.} ; {Activity date: 01/05/2017; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - REBAR FOR WALL AND TRASH ENCLOUER OK.} ; {Activity date: 12/28/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - MET WITH GC ABOUT ADA RAMP ON WEST SIDE OF BUILDING.} ; {Activity date: 12/28/2016; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WALKED SITE WITH GC WENT OVER WORK TO COMPLET FOR FINAL.} |