Permit: DP13-0191
Permit Details
Apply Date:
09/19/2013
Applicant:
Description:
SITE AND GRADING FOR NEW APARTMENT COMPLEX
Permit Reviews
Permit Number - DP13-0191
Permit Status: Complete
Permit Description: SITE AND GRADING FOR NEW APARTMENT COMPLEX
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 09/19/2013 | DEV PKG - OK TO SUBMIT | 10/04/2013 | COMPLETED |
| 10/04/2013 | SITE and/or GRADING | 11/05/2013 | COMPLETED |
| 11/13/2013 | RESUB - SITE/GRADING ALL | 11/14/2013 | COMPLETED |
| 11/14/2013 | RESUB - SITE/GRADING ALL | 12/12/2013 | COMPLETED |
| 12/12/2013 | RESUB - SITE/GRADING ALL | 12/13/2013 | COMPLETED |
Outstanding Activity Conditions
Permit Number - DP13-0191
Permit Status: Complete
Permit Description: SITE AND GRADING FOR NEW APARTMENT COMPLEX
Total Outstanding Activity Conditions - 4
| Date | Name |
|---|---|
| 12/13/2013 | The following 13 conditions apply to this grading permit DP13-0191:1)Call for Pre-construction meeting. For a PDSD Engineering Inspection, call IVR (740-6970), or schedule with a Customer Service Representative at the Planning & Development Services Department, or contact PDSD Engineering at 837-4888, or schedule inspections online at: http://www.ci.tucson.az.us/dsd/Online_Services/Online_Permits/online_permits.html 2)Copy of approved plan/permit DP13-0191 shall be kept at site at all times until final grading approval.3)These sets of plans act as the approved final grading plans for Alvord Apartments grading per approved plans sealed by Bill Schlesinger, P.E. 4)Any existing trees or transplanted trees from onsite within SVT's shall be checked and trimmed to assure they are clear of leaves and branches to a height of at least 6 ft above grade. Location of trees within existing and future SVT's may be restricted or modified as determined by City of Tucson Inspectors in order to preserve visibility. |
| 12/13/2013 | 5)Geotechnical requirements for irrigation lines near building foundations are per discussion with Pattison-Evanoff office 12DEC13. There shall be 2-3 feet minimum setback for irrigation lines from building foundation, low-water desert vegetation used, and positive surface gradient from building.6)Contact Permits and Codes (837-6606) for any questions regarding City of Tucson right-of-way permit requirements. 7)There shall be no disturbance outside of the disturbance/grading limits as shown on approved grading plans. 8)If grading construction is expected to last longer than the expiration date of the grading permit, contact PDSD to renew/extend the Grading Permit. If Final Grading Inspection has not been completed before the Grading Permit expires, and the permit has not been renewed, additional fees and reviews may be required. |
| 12/13/2013 | 9)Basin and water harvesting areas shall be fenced off so that no construction vehicular parking, no material storage, and no staging occurs in these areas, to minimize compaction or consolidation that could lessen infiltration potential. 10)PDSD Inspector should inspect special grading such as bleed pipes when under construction. 11)Revisions to the design must be discussed with a Civil Engineer at the City of Tucson Planning & Development Services Department Engineering Division, prior to any construction activity, to determine whether additional details, calculations, drainage report, or a revised grading plan is needed, or, whether changes may be provided on as-builts. All work completed without approval is subject to Stop Work Order. 12)Permittee shall notify the PDSD when the grading operation is ready for final grading inspection. Final grading approval shall not be given until all work, including installation of all drainage improvements and their permanent protective devices, and all permanent erosion control measures have been completed in accordance with the approved grading plan and grading permit, and all conditions of permit are completed. Any revegetated areas shall require Landscaping approval of established vegetation prior to Final Grading Approval. Any other exposed areas that are not reseeded shall be covered in gravel or rip rap, unless other material is proposed and reviewed by City of Tucson. |
| 12/13/2013 | 13)Project Engineering completion letters, as well as As-Builts may be required to be submitted prior to final Grading Inspection. Letters of certification from Engineer of Record, for substantial completion of drainage facilities and project substantial completion, are required to be submitted prior to final grading inspection. As-builts should include as-built elevations along drainage systems, finished pad grades, basin elevations, and other areas as deemed needed by surveyor. |
Completed Inspections
Permit Status: Complete
Permit Number: DP13-0191
Permit Description: SITE AND GRADING FOR NEW APARTMENT COMPLEX
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/24/2014 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 01/24/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 01/23/2014; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - INSTALL SWPP CONTROLS PER AP PLANS.} | |
| 01/28/2014 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 01/28/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 01/24/2014; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET SWPPP INFO SIGN.} | |
| 07/02/2015 | SITE - Stormwater Follow-up | Passed | {Activity date: 07/02/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/21/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 02/14/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} | |
| 07/02/2015 | SITE - Stormwater Final Inspection | Passed | {Activity date: 07/02/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 11/25/2015 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 11/25/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/30/2015; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - 2- 15 GAL DESERT MUSEVM PALO VERDE NEED TO BE REPLAC PER AP PLANS. INSTALL TREE STAKING PER DETAIL D ON PAGE L-7 INSTALL VACUUM BREAKERS ON ALL HOSE BIBBS.} ; {Activity date: 09/08/2015; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PLANT TREES PER DETAIL ON AP PLANS.} ; {Activity date: 07/02/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - COMPLET GEN NOTES#3 . FOR AREA WEST OF BUILDING. LIST MAY NOT BE COMPLET.} | |
| 11/25/2015 | ENGR Grading Final | Passed | {Activity date: 11/25/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 09/30/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
| 12/01/2015 | ENGR Engineering Final | Passed | {Activity date: 12/01/2015; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 11/25/2015; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE NONPOTABLE WATER AT HOSE BIBBS.} ; {Activity date: 11/23/2015; Status: Continued; Inspector: eleibol1; Comment: Entered by ELEIBOL1 - Certification letters accepted, final inspection approval pending identification of non-potable water on hose bibs.} ; {Activity date: 10/08/2015; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - DROPED OFF INFO TO GC TO COMPLET FOR FINAL.} ; {Activity date: 10/02/2015; Status: Partial Approval; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - REMOVE ALL CONSTRUCTION EQUIPMENT.FROM PARKING AREA. COMPLET ALL NOTES FROM PAST INSPECTIONS PROVIDE ENGINEER CERT AND AP AS BUILTS FROM ENGINEER OF RECORD.} ; {Activity date: 08/25/2015; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME.} ; {Activity date: 07/02/2015; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE AS-BUILTS AND CERT LETTER FROM ENGINEER OF RECORD.} |