Permit Details

Status:
Complete
Type:
Development Package
Address NEW:
9090 S HOUGHTON RD
Apply Date:
09/06/2013
Applicant:
Description:
SITE/GRADING/SWPPP - McDonald's.

Permit Reviews

Permit Number - DP13-0178
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP - McDonald's.
Start Date Submittal Complete Date Status  
05/05/2014 DEV PKG - RESUBMITTAL 06/04/2014 COMPLETED Review Details
06/04/2014 DEV PKG - RESUBMITTAL 02/09/2015 COMPLETED Review Details
06/17/2019 DEV PKG - REVISION 07/22/2019 COMPLETED Review Details
08/08/2019 REVISION - - 2ND 08/22/2019 COMPLETED Review Details
09/06/2013 DEV PKG - OK TO SUBMIT 09/06/2013 COMPLETED Review Details
09/06/2013 DEV PKG 10/07/2013 COMPLETED Review Details
10/08/2019 DEV PKG - OK TO SUBMIT 11/08/2019 COMPLETED Review Details
11/08/2019 REVISION - - 3RD 11/13/2019 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP13-0178
Permit Description: SITE/GRADING/SWPPP - McDonald's.
Total Completed Inspections - 7
Date Description Inspector Results Comments
07/08/2019 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 07/08/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Met with GC and grading contractor on site went over Approved plans.} ; {Activity date: 05/09/2016; Status: Continued; Inspector: MRUSSO; Comment: Entered by MRUSSO1 - NO CONTACT ON SITE, CALLED OFFICE LEFT MESSAGE} ; {Activity date: 10/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY NO CHANGES} ; {Activity date: 08/17/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY NO CONSTRUCTION} ; {Activity date: 04/03/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SOME DEMO WORK AND SET UP IS ON SITE, CONSTRUCTION TO START SOON} ; {Activity date: 03/06/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY AT THIS TIME} ; {Activity date: 03/02/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO CONSTRUCTION AT THIS TIME} ; {Activity date: 02/24/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 01/21/2015; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY} ; {Activity date: 12/16/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/09/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY, NO CONSTRUCTION} ; {Activity date: 11/21/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY} ; {Activity date: 10/29/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVTIVITY} ; {Activity date: 09/25/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY OR CONSTURCTION} ; {Activity date: 09/04/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY, NO CONSTRUCTION} ; {Activity date: 08/05/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY, NO CONSTRUCTION} ; {Activity date: 01/30/2014; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY/NO CONSTRUCTION AT THIS TIME} ; {Activity date: 10/23/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - NO ACTIVITY/NO CONSTRUCTION}
11/14/2019 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 11/14/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 09/10/2019; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - Landscaping has not started on this project.}
11/14/2019 ENGR Engineering Final Passed {Activity date: 11/14/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
11/14/2019 SITE - Stormwater Follow-up Passed {Activity date: 11/14/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - } ; {Activity date: 07/18/2019; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.}
11/14/2019 ENGR Grading Final Passed {Activity date: 11/14/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - This is inspections for permit T14CM00877 the building}
11/14/2019 SITE - Stormwater Final Inspection Passed {Activity date: 11/14/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }
11/14/2019 SITE - Stormwater Setup and Controls Passed {Activity date: 11/14/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by DMERANZ1 - }

Documents

File Name Document Type  
REV-2_PLAN SET.PDF DOCUMENTS VIEW
REV-3_DEVELOPMENT PKG 2019-11-05-SIGNED.PDF DOCUMENTS VIEW
1-16 OF 16.PDF DEVELOPMENT PACKAGE VIEW
None DOCUMENTS VIEW
PERMIT_EXTENSION.PDF DOCUMENTS VIEW
None DOCUMENTS VIEW
REVISION LETTER, 06.10.19.PDF DOCUMENTS VIEW
REVISION LETTER, 08.07.19.PDF DOCUMENTS VIEW
LETTER-SIGNED, 11.05.19.PDF DOCUMENTS VIEW