Permit Details

Status:
Complete
Type:
Development Package
Address:
6220 S TUCSON BL
Address NEW:
6220 S TUCSON BL
Apply Date:
08/19/2013
Applicant:
Lisa Bowers
Description:
SITE/GRADING

Permit Reviews

Permit Number - DP13-0156
Permit Status: Complete
Permit Description: SITE/GRADING
Start Date Submittal Complete Date Status  
06/09/2014 REVISION - GRADING 06/09/2014 COMPLETED Review Details
06/09/2014 REVISION - SITE 06/17/2014 COMPLETED Review Details
08/19/2013 DEV PKG - OK TO SUBMIT 08/19/2013 COMPLETED Review Details
08/19/2013 SITE and/or GRADING 10/24/2013 COMPLETED Review Details
10/24/2013 RESUB - SITE/GRADING ALL 11/14/2013 COMPLETED Review Details
11/14/2013 RESUB - SITE/GRADING ALL 11/14/2013 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP13-0156
Permit Description: SITE/GRADING
Total Completed Inspections - 8
Date Description Inspector Results Comments
11/19/2013 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 11/19/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONVERNS AT THIS TIME.}
11/27/2013 SITE - Stormwater Setup and Controls Passed {Activity date: 11/27/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 11/19/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - INSTALL SWPPP INFO AT GATE .INSTALL TRACK OUT AND COMPLET SWPP CONTROLS. DROPED OFF PRE-CON PACKET TO FILL OUT.}
06/12/2014 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 06/12/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
06/12/2014 PDSD Site/Engineering Division - NPPO Passed {Activity date: 06/12/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/03/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE MONITORING REPORT.}
06/12/2014 ENGR Engineering Final Passed {Activity date: 06/12/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 06/03/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - PROVIDE CERT LETTER FOR ALL GRADING AND DRAINAGE FROM ENGINEER AND AS-BUILTS FOR ALL CHANGES. PROVIDE STABILIZATION TO ALL AREAS DISTURBED FROM CONSTRUCTION. LIST MAY NOT BE COMPLET.}
06/12/2014 SITE - Stormwater Follow-up Passed {Activity date: 06/12/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 02/21/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 01/31/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WASH OUT HAS BEEN REMOVED.} ; {Activity date: 01/24/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.} ; {Activity date: 01/08/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - TRACK OUT ROCK HAS BEEN INSTALLED AT GATE.} ; {Activity date: 01/06/2014; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GC NOT ON SITE. NO ROCK AT GATE THAT IS OPEN.} ; {Activity date: 12/30/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GOT WITH GC ABOUT TRACK OUT ROCK NOT AT GATE THAT IS OPEN.} ; {Activity date: 12/16/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.} ; {Activity date: 12/12/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO CONCERNS AT TIS TIME.} ; {Activity date: 12/05/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - NO ACTIVITY ON SITE.} ; {Activity date: 11/27/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
06/12/2014 ENGR Grading Final Passed {Activity date: 06/12/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
06/12/2014 SITE - Stormwater Final Inspection Passed {Activity date: 06/12/2014; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }