Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 06/12/2014 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Approved |
Entered by RLEDONN1 - |
| 02/21/2014 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 01/31/2014 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - WASH OUT HAS BEEN REMOVED. |
| 01/24/2014 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 01/08/2014 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - TRACK OUT ROCK HAS BEEN INSTALLED AT GATE. |
| 01/06/2014 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - GC NOT ON SITE. NO ROCK AT GATE THAT IS OPEN. |
| 12/30/2013 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - GOT WITH GC ABOUT TRACK OUT ROCK NOT AT GATE THAT IS OPEN. |
| 12/16/2013 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME. |
| 12/12/2013 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT TIS TIME. |
| 12/05/2013 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
| 11/27/2013 |
SITE - Stormwater Follow-up
|
RLEDONNE |
Continued |
Entered by RLEDONN1 - |