Permit: DP13-0093
Permit Details
Status:
Complete
Type:
Development Package
Address:
9130 S HOUGHTON RD
Address NEW:
9130 S HOUGHTON RD
Apply Date:
05/24/2013
Applicant:
Description:
SITE/GRADING/SWPPPOriginally approved 8/28/2013As-builts approved 1/29/2014
Permit Reviews
Permit Number - DP13-0093
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPPOriginally approved 8/28/2013As-builts approved 1/29/2014
| Start Date | Submittal | Complete Date | Status |
|---|---|---|---|
| 01/27/2014 | REVISION - - 1ST | 01/29/2014 | COMPLETED |
| 05/24/2013 | DEV PKG - OK TO SUBMIT | 05/24/2013 | COMPLETED |
| 05/24/2013 | DEV PKG | 07/19/2013 | COMPLETED |
| 07/19/2013 | DEV PKG - RESUBMITTAL | 08/14/2013 | COMPLETED |
| 08/14/2013 | DEV PKG - RESUBMITTAL | 10/07/2013 | COMPLETED |
| 12/18/2013 | REVISION - SITE | 01/22/2014 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP13-0093
Permit Description: SITE/GRADING/SWPPPOriginally approved 8/28/2013As-builts approved 1/29/2014
Total Completed Inspections - 7
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 11/06/2013 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 11/06/2013; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - SITE IS LESS THAN 1 AC THEREFORE NO SWPPP REQUIRED. CONTRACTOR WORKING ON BLDG, NO SITE WORK. ENSURE SITE IS CONSTRUCTED PER PLAN } |
|
| 03/05/2014 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 03/05/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 03/05/2014 | ENGR Engineering Final | Passed | {Activity date: 03/05/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 03/05/2014 | SITE - Stormwater Follow-up | Passed | {Activity date: 03/05/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } ; {Activity date: 12/12/2013; Status: Continued; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 03/05/2014 | ENGR Grading Final | Passed | {Activity date: 03/05/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 03/05/2014 | SITE - Stormwater Final Inspection | Passed | {Activity date: 03/05/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } | |
| 03/05/2014 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 03/05/2014; Status: Approved; Inspector: MRUSSO; Comment: Entered by DROBERT5 - } |