Permit: DP12-0215
Permit Details
Apply Date:
11/15/2012
Applicant:
Lisa Bowers
Description:
SITE/GRADING/SWPPP- RAYTHEON MODULAR DATA CENTER
Permit Reviews
Permit Number - DP12-0215
Permit Status: Complete
Permit Description: SITE/GRADING/SWPPP- RAYTHEON MODULAR DATA CENTER
Start Date | Submittal | Complete Date | Status |
---|---|---|---|
01/15/2013 | REVISION - SITE | 02/21/2013 | COMPLETED |
02/21/2013 | REVISION - SITE | 02/22/2013 | COMPLETED |
02/22/2013 | REVISION - SITE | 03/04/2013 | COMPLETED |
11/15/2012 | DEV PKG - OK TO SUBMIT | 11/15/2012 | COMPLETED |
11/15/2012 | SITE and/or GRADING | 12/03/2012 | COMPLETED |
12/07/2012 | RESUB - SITE and/or GRADING | 12/11/2012 | COMPLETED |
Completed Inspections
Permit Status: Complete
Permit Number: DP12-0215
Permit Description: SITE/GRADING/SWPPP- RAYTHEON MODULAR DATA CENTER
Total Completed Inspections - 11
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/14/2012 | PDSD Engineering Division Pre-Construction SITE | Passed | {Activity date: 12/14/2012; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - DROPPED OFF PER-CON PACKET TO DICK.} | |
01/17/2013 | SITE - Stormwater Setup and Controls | Passed | {Activity date: 01/17/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 12/19/2012; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | PDSD Site/Engineering Division - Landscaping | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | SITE - SWPPP Correction Notice | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | ENGR Engineering Final | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | SITE - Stormwater Follow-up | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | ENGR Grading Final | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 03/01/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WALKED SITE WITH JASON GREEN.} ; {Activity date: 02/28/2013; Status: Continued; Inspector: jgreen; Comment: Entered by JGREEN2 - Revision #2. Revised the grading and location of the building pad and the basin due to access and grading around existing underground fiber optics that are "classified" JG} | |
07/16/2013 | SITE - SWPPP Violation Notice | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | SITE - Stormwater Final Inspection | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 05/08/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
07/16/2013 | COT - ENGR - Site - Assurance Release | Passed | {Activity date: 07/16/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } | |
10/28/2014 | RSBU - Building Final | Passed | {Activity date: 10/28/2014; Status: Approved; Inspector: kmedina; Comment: Entered by KMEDINA1 - } |