Permit Number - DP12-0118
Permit Status: Complete
Permit Description: DOLLAR GENERAL AT AJO AND PANDORA
Start Date Submittal Complete Date Status  
07/19/2012 DEV PKG - OK TO SUBMIT 07/19/2012 COMPLETED Review Details
07/19/2012 DEV PKG 09/19/2012 COMPLETED Review Details
09/19/2012 DEV PKG - RESUBMITTAL 10/25/2012 COMPLETED Review Details
10/25/2012 DEV PKG - RESUBMITTAL 12/14/2012 COMPLETED Review Details

Completed Inspections

Permit Status: Complete
Permit Number: DP12-0118
Permit Description: DOLLAR GENERAL AT AJO AND PANDORA
Total Completed Inspections - 10
Date Description Inspector Results Comments
01/17/2013 PDSD Engineering Division Pre-Construction SITE Passed {Activity date: 01/17/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 01/04/2013; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - GEN CONTRACTOR NOT ON SITE DROPED OFF PER-CON PACKET. AND WALKED SITE WITH GRADING CONTRATOR.} ; {Activity date: 01/03/2013; Status: Not ready for Inspection; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - CONTRACTOR NOT ON SITE.} ; {Activity date: 12/31/2012; Status: Not ready for Inspection; Inspector: DROBERTS; Comment: Entered by DROBERT5 - NO ONE ONSITE AT THIS TIME, RON WILL REVISIT THE SITE ON WEDNESDAY WHILE THE CONTRACTOR IS WORKING.}
04/04/2013 SITE - SWPPP Correction Notice Passed {Activity date: 04/04/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/04/2013 SITE - Stormwater Follow-up Passed {Activity date: 04/04/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/04/2013 ENGR Grading Final Passed {Activity date: 04/04/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/04/2013 SITE - SWPPP Violation Notice Passed {Activity date: 04/04/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/04/2013 SITE - Stormwater Final Inspection Passed {Activity date: 04/04/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/04/2013 SITE - Stormwater Setup and Controls Passed {Activity date: 04/04/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }
04/11/2013 PDSD Site/Engineering Division - Landscaping Passed {Activity date: 04/11/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/02/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - INSTALL LANDSCAPING PER APPROVED PLANS.}
04/11/2013 ENGR Engineering Final Passed {Activity date: 04/11/2013; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - } ; {Activity date: 04/09/2013; Status: Continued; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - WALKED SITE WITH DAVE AND GC.}
06/12/2019 RSBU - Building Final Passed {Activity date: 06/12/2019; Status: Approved; Inspector: RLEDONNE; Comment: Entered by RLEDONN1 - }

Documents

File Name Document Type  
001_ SHEET 1 OF 9.TIF GRADING PLANS VIEW
002_SHEET 2 OF 9.TIF GRADING PLANS VIEW
003_SHEET 3 OF 9.TIF GRADING PLANS VIEW
004_SHEET 4 OF 9.TIF GRADING PLANS VIEW
005_SHEET 5 OF 9.TIF GRADING PLANS VIEW
006_L-6.TIF GRADING PLANS VIEW
007_L-7.TIF GRADING PLANS VIEW
008_L-8.TIF GRADING PLANS VIEW
009_L-9.TIF GRADING PLANS VIEW
None DOCUMENTS VIEW
CERTIFICATION LETTER 2013_4_9.PDF DOCUMENTS VIEW