Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Parcel Search: 141148150
Parcel Search
Parcel Attributes
Parcel | 141148150 |
---|---|
Jurisdiction | Tucson |
City of Tucson Zoning | C-1 |
Tucson Ward | Ward 4 |
Tucson Registered Neighborhood | Rita Ranch |
Major Streets & Routes | Arterial or Collector ,Gateway Route ,Intersection Buffer |
Pima County Data | Assessor, Recorder, Treasurer, ... |
Parcel Map | Map |
Addresses |
Annexations & Original City Zoning (OCZ)
Date - 11/23/2024 7:09 a.m.
Total Number Of OZC Plans - (1)
Special Development Requests & Requirements
Date - 11/23/2024 7:09 a.m.
Total Number Of Special Development Permits - (7)
Activity Number | Status | Apply Date | Expired Date | Type | Description |
---|---|---|---|---|---|
H000000320 | Closed | N/A | |||
H000001744 | Closed | N/A | |||
H000001745 | Closed | N/A | |||
H000001746 | Closed | N/A | |||
T08SA00349 | Void | N/A | |||
T10SA00199 | Closed | N/A | LIQUOR MITIGATION PLAN FOR RESTAURANT WITH NEW PATIO EXPANSION LOCATED WITHIN 300 FEET OF RESIDENTIAL (SUBURBAN RANCH - SR) ZONING. | ||
T17SA00017 | Complete | N/A |
Permits
Parcel Number - 141148150
Date - 11/23/2024 7:09 a.m.
Total Number Of Permits - (488)
Permit | Permit Status | Entered Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
T20OT00015 | Submitted | 01/03/2020 | N/A | 112 | Sign - Annual Portable | BANNER 45 DAYS |
TZ-CMP-0124-00002 | Complete | 01/03/2024 | N/A | Zoning Compliance | Zoning Confirmation Letter for Safeway at 9050 East Valencia Road | |
T18OT00030 | Expired | 01/08/2018 | 10/10/2018 | 112 | Sign - Annual Portable | 7 LOCATIONS IN TUCSON 9040 E VALENCIA / 1570 E TUCSON / 8110 S HOUGHTON RD. / 3225 E SWAN RD / 8004 |
TS-PRM-0123-00155 | Complete | 01/26/2023 | 03/23/2024 | Sign - Permanent | One wall sign with illuminated pan channel letters | |
T22OT00114 | Expired | 02/15/2022 | 08/14/2022 | 172 | Sign - Permanent | 1-illum wall sign |
TF-FOP-0423-00811 | Complete | 04/05/2023 | 07/06/2023 | Fire Operational Permit | INDOOR RETAIL FIREWORKS SALES 131# | |
TF-FOP-0424-00517 | Complete | 04/26/2024 | 07/07/2024 | Fire Operational Permit | Retail sales - CFW - special event vendor | |
TF-FOP-0524-00629 | Complete | 05/24/2024 | 07/07/2024 | Fire Operational Permit | TNT CFW sales - special events organizer | |
TF-FOP-0524-00638 | Complete | 05/29/2024 | 07/07/2024 | Fire Operational Permit | TNT CFW sales - Tent - Special event vendor | |
TF-FCP-0624-00411 | Inspections | 06/01/2024 | 12/14/2024 | Fire Construction Permit | Upgrade of existing commercial kitchen hood fire suppression system to protect new equipment being installed under the hood. | |
T22OT00424 | Expired | 06/09/2022 | 05/05/2023 | 106 | Sign - Permanent | 1-ILLUM WALL SIGN |
T19OT00703 | Issued | 07/30/2019 | 09/14/2019 | 112 | Sign - Annual Portable | 45 DAY BANNER EXP ON SEPT 14 2019 |
T22RW03219 | Complete | 09/06/2022 | 11/13/2022 | Right-of-Way (ROW) | EXCAVATE APPROX A 176’X5’ & 90’X5’ TRENCHES IN ASPHALT TO REPLACE GAS MAIN AT 9040 E VALENCIA RD. EX; Work Order: 4468479 | |
TS-PRM-0924-00423 | Issued | 09/25/2024 | 03/24/2025 | UNIT 112 | Sign - Permanent | Installation and manufacture of 1 illuminated wall sign |
D00-0062 | Canceled | 10/04/2000 | 12/03/2001 | Development Package | RITA RANCH RETAIL CENTER | |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project | |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 1 UNIT 1208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 10 UNIT 10208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 11 UNIT 11308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 12 UNIT 12308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 13 UNIT 13308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 14 UNIT 14308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 15 UNIT 15308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 16 UNIT 16308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 17 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 18 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2301 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2302 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2303 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2304 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2305 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2306 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2307 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 2 UNIT 2308 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 3 UNIT 3208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 4 UNIT 4208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 5 UNIT 5208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 6 UNIT 6208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 7 UNIT 7208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 8 UNIT 8208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9101 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9102 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9103 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9104 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9105 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9107 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9108 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9201 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9202 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9203 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9204 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9205 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9206 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9207 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | BLDG 9 UNIT 9208 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 100 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 106 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 110 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 112 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 118 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 120 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 124 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 130 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 136 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 140 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 142 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 150 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 160 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 166 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 172 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 178 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 184 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 188 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TR-ROW-1123-01353 | Complete | 11/14/2023 | 12/27/2023 | UNIT 196 | Right-of-Way (ROW) | Air-Vacuum excavation of 12 utility potholes for the design phase of Tucson DOT Valencia Road: Kolb Road to Houghton Road project |
TF-FOP-1122-00108 | Complete | 11/17/2022 | 05/17/2023 | Fire Operational Permit | INDOOR RETAIL SALES OF STATE PERMISSIBLE FIREWORKS. | |
TF-FOP-1223-01893 | Complete | 12/07/2023 | 01/03/2024 | Fire Operational Permit | INDOOR RETAIL SALE | |
T04BU02561 | Closed | 10/19/2004 | 04/20/2005 | SPKLR | FIRE SPRINKLER:ADD 2 RELOCATE 2 | |
T04CM05376 | C of o | 12/14/2004 | 01/24/2006 | #172 | COMBO | TI:ICE CREAM SHOP |
T04OT01955 | Final | 09/28/2004 | 05/08/2005 | SIGN | SIGN:7844 US BANK #1986 | |
T05AN00637 | Void | 06/13/2005 | N/A | #196 | ADDRNEW | |
T05AN00652 | Issued | 06/15/2005 | N/A | #188 | ADDRNEW | |
T05BU01230 | Final | 05/18/2005 | 11/15/2005 | #172 | SPKLR | FIRE SPKR: RELOCATE 4 |
T05CM02730 | C of o | 06/14/2005 | 03/06/2006 | #196* | COMBO | TI:RESTAURANT |
T05CM05879 | Si_xpire | 11/23/2005 | 01/23/2007 | COMBO | TI: RETAIL | |
T05OT00331 | Final | 02/14/2005 | 01/23/2006 | #172 | SIGN | SIGN: 8510 SCOOP'S |
T05OT02083 | Final | 08/22/2005 | 02/20/2006 | #196* | SIGN | SIGN: 9564 KYO SUSHI |
T05OT02552 | Final | 10/13/2005 | 11/19/2006 | #196* | SIGN | SIGN:# 9881 |
T06BU00977 | Final | 04/24/2006 | 01/10/2007 | SPKLR | SPRINKLER: | |
T06BU01416 | Final | 06/06/2006 | 12/04/2006 | BUILD | PRE PACKAGED FIRE SUPPRESSION SYSTEM | |
T06BU01628 | Final | 06/22/2006 | 12/26/2006 | BUILD | KITCHEN EXHAUST HOOD FIRE SUPPRESSION SYSTEM | |
T06OT00669 | Final | 03/09/2006 | 08/25/2008 | #172 | SIGN | 10784 |
T06OT01884 | Final | 07/18/2006 | 02/17/2007 | SIGN | 11508 | |
T06OT01885 | Final | 07/18/2006 | 03/04/2007 | SIGN | 11509 | |
T06OT01886 | Final | 07/18/2006 | 01/30/2007 | SIGN | 11510 | |
T07OT01129 | Final | 05/11/2007 | 12/22/2007 | #112 | SIGN | 13111 |
T08AN00993 | Issued | 12/12/2008 | N/A | #118 | ADDRNEW | |
T08BU01932 | Final | 10/30/2008 | 05/03/2009 | SPKLR | Add 2 fire sprinkler heads. | |
T08CM02958 | C of o | 09/03/2008 | 06/22/2009 | #136 | COMBO | TI: RESTAURANT |
T08CM03439 | C of o | 10/21/2008 | 08/31/2009 | #118 | COMBO | TI: ANIMAL SERVICES |
T08EL01259 | Final | 07/07/2008 | 02/17/2009 | ELECT | SERVICE REPAIR | |
T08OT01057 | Final | 05/01/2008 | 12/13/2008 | SIGN | 14914 | |
T08OT01058 | Expired | 05/01/2008 | 05/03/2010 | SIGN | 14913 | |
T08OT01131 | Final | 05/09/2008 | 12/21/2008 | #112 | SIGN | 14962 |
T08OT02727 | Final | 11/18/2008 | 06/13/2010 | SIGN | 15922 | |
T08OT02808 | Final | 11/26/2008 | 09/01/2009 | #136 | SIGN | 15973 |
T08OT02931 | Final | 12/16/2008 | 09/05/2009 | #118 | SIGN | 16049 |
T09BU00195 | Final | 02/09/2009 | 08/17/2009 | #118 | SPKLR | Add 12, relocate 20 fire sprinklers |
T09BU01355 | Final | 09/10/2009 | 05/08/2010 | #196* | SPKLR | Relocate 2 fire sprinklers |
T09CM00107 | Expired | 01/15/2009 | 01/11/2010 | COMBO | ADD: EXTERIOR AWNING, BASIC FACADE WORK, EXTERIOR ELECTRICAL LIGHTS | |
T09OT00072 | Final | 01/14/2009 | 08/30/2009 | #112 | SIGN | 16162 |
T09OT00112 | Final | 01/20/2009 | 07/28/2009 | #118 | SIGN | 16188 |
T09OT00795 | Final | 04/23/2009 | 01/16/2010 | #100 | SIGN | 16566 |
T09OT01116 | C of o | 06/02/2009 | 12/05/2009 | #100 | C-OF-O | C OF O:RESTAURANT |
T09OT02142 | Closed | 10/06/2009 | 05/30/2010 | SIGN | 17307 | |
T09OT02750 | C of o | 12/17/2009 | 06/21/2010 | #106 | C-OF-O | C OF O:RETAIL |
T09OT02779 | Final | 12/22/2009 | 07/11/2010 | SIGN | 17680 | |
T09OT02813 | Final | 12/29/2009 | 08/16/2010 | #106 | SIGN | 17705 |
T09OT02814 | Expired | 12/29/2009 | 07/06/2010 | #106 | SIGN | 17704 |
T10CFW0038 | Closed | 12/09/2010 | 06/07/2011 | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE*CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTION | |
T10OT00086 | Final | 01/12/2010 | 08/29/2010 | #112 | SIGN | 17778 |
T10OT00494 | Final | 03/05/2010 | 09/18/2010 | #118 | SIGN | 18005 |
T10OT01621 | Final | 07/29/2010 | 03/14/2011 | #112 | SIGN | 18703 |
T10OT02703 | Final | 12/22/2010 | 08/22/2011 | #112 | SIGN | BANNER 45DAYS START: 01/05/11 END: 02/19/11 |
T11BU00845 | Final | 06/22/2011 | 12/24/2011 | TENTS | TENT FOR FIREWORKS | |
T11BU01021 | Final | 08/03/2011 | 03/06/2013 | SPKLR | Add 5 fire sprinklers | |
T11BU01249 | Expired | 09/27/2011 | 04/03/2012 | SPKLR | RELOCATE ONE FIRE SPRINKLER. | |
T11CFW0034 | Final | 05/17/2011 | 11/13/2011 | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE & STORAGE | |
T11CFW0102 | Final | 06/22/2011 | 12/24/2011 | FIREWRKS | FIREWORKS | |
T11CFW0117 | Final | 12/05/2011 | 06/02/2012 | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE & STORAGE | |
T11CM02022 | Final | 06/29/2011 | 03/06/2013 | COMBO | TI; PHARMACY | |
T11CM03176 | C of o | 10/04/2011 | 06/13/2012 | #100 | COMBO | TI: EL CORONADO RESTAURANT |
T11OT01466 | Final | 07/26/2011 | 03/18/2012 | #112 | SIGN | BANNER 45 DAYS 7-25-2011 THRU 9-14-2011 |
T12BU00315 | Final | 03/07/2012 | 10/01/2012 | BUILD | FIRE ALARM | |
T12BU01492 | Expired | 12/18/2012 | 06/16/2013 | TENTS | TENT | |
T12CFW0041 | Final | 05/09/2012 | 11/05/2012 | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE: CONTACT TFD 791-4502 | |
T12CFW0074 | Final | 11/23/2012 | 05/22/2013 | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE:CONTACT TFD 791-4502 FOR REQUIRED INSPECTION | |
T12CFW0128 | Final | 12/11/2012 | 11/02/2013 | FIREWRKS | FIREWORKS | |
T12OT00059 | Final | 01/11/2012 | 08/26/2012 | SIGN | BANNER:45 DAYS 01-11-2012 - 02-26-12 | |
T12OT01117 | Final | 07/27/2012 | 03/11/2013 | SIGN | BANNER:45 DAYS 07-27-2012 - 09-10-12 | |
T12OT01327 | Expired | 09/13/2012 | 03/17/2013 | #178 | SIGN | 1- ILLUM WALL SIGN 20738 |
T13CFW0027 | Final | 05/07/2013 | 11/03/2013 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTIONS | |
T13CFW0117 | Final | 12/12/2013 | 06/10/2014 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTIONS | |
T13CM02054 | C of o | 04/09/2013 | 11/02/2013 | #196 | COMBO | TI: PET GROOMING |
T13CM05154 | Final | 08/21/2013 | 03/12/2014 | #172 | COMBO | TI: COMM |
T13CM06987 | L of c | 11/18/2013 | 09/30/2014 | #142 | COMBO | TI: RETAIL |
T13OT00006 | Final | 01/03/2013 | 08/20/2013 | #112 | SIGN | BANNER - 45 DAY 01/04/13 THRU 02/18/13 |
T13OT00562 | Expired | 05/09/2013 | 11/11/2013 | #196 | SIGN | 1- ILLUM. WALL SIGN 21226 |
T13OT00883 | Final | 07/29/2013 | 03/16/2014 | #112 | SIGN | 45 DAY BANNER 07/31/13 THRU 09/14/13 |
T13OT01067 | Expired | 09/09/2013 | 08/20/2014 | #172 | SIGN | 1- ILLUM WALL SIGN |
T13OT01069 | Void | 09/10/2013 | N/A | #172 | SIGN | SIGN |
T14BU00112 | Final | 01/29/2014 | 08/24/2014 | #142 | SPKLR | FIRE SPRINKLER |
T14CFW0004 | Final | 05/09/2014 | 11/05/2014 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTIONS | |
T14CFW0094 | Final | 12/03/2014 | 06/01/2015 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTIONS | |
T14OT00016 | Final | 01/06/2014 | 02/21/2014 | #112 | SIGN | BANNER - 45 DAYS 01/07/2014 THRU 02/21/2014 |
T14OT00213 | Expired | 02/18/2014 | 08/19/2014 | #142 | SIGN | 2- IDENTICAL ILLUM WALL SIGNS ON THE N. & E. ELEVS |
T14OT00493 | Expired | 04/21/2014 | 10/27/2014 | #100 | SIGN | AFRAME ON PRIVATE PROPERTY (12' SETBACK) |
T15BU00373 | Expired | 04/06/2015 | 11/03/2015 | #184 | BUILD | HOOD EXHAUST SYSTEM |
T15BU00730 | Expired | 06/25/2015 | 12/28/2015 | #184 | BUILD | FIRE ALARM |
T15CFW0028 | Final | 05/01/2015 | 10/28/2015 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTIONS | |
T15CFW0098 | Final | 11/25/2015 | 05/23/2016 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 520-791-4502 FOR THE REQUIRED INSPECTIONS. | |
T15CM01347 | L of c | 03/02/2015 | 11/10/2015 | #188 | COMBO | REMODEL EXISTING RESTAURANT |
T15CM04339 | Withdrwn | 06/25/2015 | N/A | #184 | COMBO | TI: RESTAURANT |
T15OT00454 | Expired | 04/03/2015 | 10/13/2015 | #188 | SIGN | 1- ILLUM WALL SIGN |
T15OT00630 | Closed | 05/08/2015 | 02/13/2016 | #112 | SIGN | BANNER 05/14/15-08/12/2015 |
T15OT00661 | Withdrwn | 05/14/2015 | N/A | #188 | C-OF-O | C OF O |
T16CFW0027 | Final | 05/16/2016 | 11/12/2016 | FIREWRKS | *APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE* CONTACT TFD 791-4502 FOR THE REQUIRED INSPECTIONS | |
T16CFW0096 | Final | 11/30/2016 | N/A | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE IN BUILDING. CONTACT TFD 791-4502 FOR THE REQUESTED INSPECTIONS. | |
T16CFW0097 | Final | 12/01/2016 | N/A | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE IN BUILDING. CONTACT TFD 791-4502 FOR THE REQUESTED INSPECTIONS. | |
T16CM05215 | C of o | 07/06/2016 | 01/09/2017 | #160 | COMBO | RETAIL SMOKE SHOP |
T16OT00007 | Closed | 01/05/2016 | 02/11/2017 | #112 | SIGN | 45DAY BANNER 01/05/16 - 02/19/16 |
T16OT00887 | Expired | 07/21/2016 | 01/17/2017 | #160 | SIGN | 1- ILLUM WALL SIGN |
T16OT00895 | Expired | 07/22/2016 | 03/13/2017 | #112 | SIGN | banner |
T17CFW0027 | Final | 05/04/2017 | 01/01/2018 | FIREWRKS | APPROVED FIREWORKS PERMIT FOR SALE AND STORAGE IN BUILDING. APPROVED TFD SIGNAGE MUST BE POSTED. CONTACT TFD 791-4502 FOR THE REQUESTED INSPECTIONS PRIOR TO BEGINNING SALES. | |
T17CFW0103 | Final | 12/05/2017 | 07/06/2018 | FIREWRKS | FIREWORKS | |
T17OT00006 | Closed | 01/03/2017 | 08/20/2017 | #112 | SIGN | 45 banner permit exp 2/18/2017 |
T17OT00762 | Closed | 07/25/2017 | 09/24/2018 | #112 | SIGN | BANNER 45 DAYS |
T18CFW0023 | Final | 05/03/2018 | 01/01/2019 | FIREWRKS | FIREWORKS | |
T18CFW0096 | Final | 11/20/2018 | 06/22/2019 | FIREWRKS | FIREWORKS PERMIT- TNT DATE OF EVENT: 12.10.18- 01.03.19 SAFEWAY 520-663-0009 | |
T18OT00795 | Final | 07/23/2018 | 04/02/2019 | #112 | SIGN | 45 day banner expires on Sept 8th 2018 |
T18OT01190 | Final | 11/16/2018 | 07/17/2019 | #100 | SIGN | 1-ILLUM WALL SIGN |
T19CFW0025 | Final | 04/23/2019 | 12/31/2019 | FIREWRKS | FIREWORKS 520-663-0009 | |
T19CFW0096 | Final | 12/02/2019 | 07/04/2020 | FIREWRKS | TNT CONSUMER FIREWORKS 12/18-01/03 | |
T19CM09057 | L of c | 12/11/2019 | 07/21/2020 | COMBO | INTERIOR DEMO - US BANK IN SAFEWAY | |
T19FC00007 | Final | 01/03/2019 | 07/07/2019 | #100 | FIRECONS | RE-PIPE EXISTING FIRE SYSTEM |
T19OT00006 | Closed | 01/04/2019 | 10/20/2019 | #112 | SIGN | 45 DAY pennant EXP ON February 23, 2019 |
T19OT00657 | Final | 07/16/2019 | 01/22/2020 | #166 | SIGN | 1-ILLUM WALL SIGN |
T19RW06374 | Final | 10/22/2019 | 12/25/2019 | ROW | 722' FT OF BORE,16 SQFT OF CONCRETE REMOVAL/REPLACEMENT AND PLACEMENT OF HH. BUS STOP IN THE AREA, CONTACT SUN TRAN, BEA PAULUS AT 520-206-8826 AND/OR CHRISTINA ROCK AT 520-206-8934 FOR COORDINATION. | |
T20CFW0001 | Final | 05/12/2020 | 12/29/2020 | FIREWRKS | Fireworks- Consumer at Safeway 1986 05/20-07/06/2020 | |
T20CFW0105 | Final | 11/30/2020 | 06/29/2021 | FIREWRKS | SAFEAY TNT FIREWORKS 12/10-01/03/2021 | |
T20CM06193 | Revoked | 09/10/2020 | 04/12/2021 | COMBO | COOKING OIL SYSTEM, LINES & FILL BOX | |
T20FC00037 | Final | 01/16/2020 | 07/19/2020 | FIRECONS | *** NO PLANS *** Relocate Two Pendants | |
T21CFW0038 | Final | 05/17/2021 | 12/18/2021 | FIREWRKS | CONSUMER FIREWORKS- TNT FIREWORKS SAFEWAY #1986 520-663-0009 | |
T21CFW0098 | Final | 12/06/2021 | 06/19/2022 | FIREWRKS | CONSUMER FIREWORKS - SAFEWAY 1986 - 9050 E VALENCIA RD (520)663-0009 | |
T21CM05141 | Final | 06/21/2021 | 03/29/2022 | COMBO | TI:SAFEWAY (T21DV01801) | |
T21FO00018 | Final | 01/07/2021 | 09/28/2021 | FIREOPER | SAFEWAY INC | |
T21FO00021 | Void | 01/12/2021 | 01/12/2022 | FIREOPER | SAFEWAY 267 | |
T22CFW0027 | Final | 04/25/2022 | 10/30/2022 | FIREWRKS | CFW 5/9/22 TO 7/6/22 - SAFEWAY #1986 - 9050 E VALENCIA RD |
Code Enforcement
Parcel Number - 141148150
Date - 11/23/2024 7:09 a.m.
Total Number Of Code Cases - 37
Case Number | Case Status | Entered Date | Closed Date | Unit | Type | Description |
---|---|---|---|---|---|---|
T05FR00221 | Complete | 02/09/2005 | N/A | FIREINSP | ALARM SYSTEM O/S SINCE 9/25/04. | |
T05FR00945 | Complete | 06/22/2005 | N/A | #160 | FIREINSP | self inspection program |
T06FR00247 | Field | 02/28/2006 | N/A | FIREINSP | full insp" SIP | |
T06FR01149 | Complete | 05/03/2006 | N/A | FIREINSP | self inspection program. | |
T07FR00989 | Complete | 05/22/2007 | N/A | FIREINSP | Full Inspection | |
T07FR01012 | Field | 05/25/2007 | N/A | FIREINSP | Full Inspection | |
T07FR02266 | Complete | 11/08/2007 | N/A | FIREINSP | F/U on Complaint | |
T08FR00303 | Complete | 01/28/2008 | N/A | #142 | FIREINSP | General Inspection |
T08FR00305 | Complete | 01/29/2008 | N/A | FIREINSP | Code Violation | |
T08FR00306 | Complete | 01/29/2008 | N/A | #160 | FIREINSP | General Inspection |
T08FR00307 | Complete | 01/29/2008 | N/A | #166 | FIREINSP | General Inspection |
T08FR00317 | Complete | 01/31/2008 | N/A | #178 | FIREINSP | General Inspection |
T08FR00318 | Complete | 01/31/2008 | N/A | #172 | FIREINSP | General Inspection |
T08FR00335 | Complete | 02/04/2008 | N/A | #136 | FIREINSP | General Inspection |
T08FR00355 | Complete | 02/04/2008 | N/A | #188 | FIREINSP | General Inspection |
T08FR00372 | Complete | 02/05/2008 | N/A | #130 | FIREINSP | General Inspection |
T08FR00373 | Complete | 02/05/2008 | N/A | #118 | FIREINSP | General Inspection |
T08FR00391 | Complete | 02/07/2008 | N/A | #112 | FIREINSP | General Inspection |
T08FR00501 | Complete | 02/19/2008 | N/A | #106 | FIREINSP | General Inspection |
T09FR00297 | Complete | 01/22/2009 | N/A | #166 | FIREINSP | SELF INSPECTION PROGRAM |
T09FR00341 | Complete | 01/26/2009 | N/A | #160 | FIREINSP | SELF INSPECTION PROGRAM |
T09FR01397 | Complete | 04/23/2009 | N/A | #178 | FIREINSP | SELF INSP |
T09FR01516 | Complete | 05/01/2009 | N/A | FIREINSP | Full Fire Inspection | |
T09FR01827 | Complete | 05/29/2009 | N/A | FIREINSP | 2 B-range not protected, report in log book | |
T09FR02128 | Complete | 06/29/2009 | N/A | FIREINSP | FIRE ALARM SYSTEM COMPLAINT | |
T10DV01735 | Noverify | 03/30/2010 | N/A | DNR_VIOL | VALENCIA ANIMAL HOSPITAL HAS A ILLEGAL A-FRAME SIGN NEAR SIDEWALK WITH BALLOONS TIED TO IT. | |
T10FR00812 | Complete | 04/27/2010 | N/A | FIREINSP | Self Inspection | |
T10FR00992 | Complete | 05/17/2010 | N/A | #160 | FIREINSP | Self inspection prgram |
T10FR01357 | Complete | 07/15/2010 | N/A | FIREINSP | DISCREPANCIES - CINTAS | |
T10FR02658 | Complete | 12/16/2010 | N/A | FIREINSP | FIREWORKS INSPECTION | |
T14DV04879 | Complian | 07/16/2014 | N/A | DNR_VIOL | 1 FEATHER BANNER (EL CORONADO RESTAURANT) | |
T14DV07272 | Complian | 09/12/2014 | N/A | DNR_VIOL | illegal signs - one feather banner, one banner hanging from canopy and without permit. One A- frame sign that is legally permitted and appears to have proper size and placement but has an illegal paper attachment. PRO to feather banner. | |
T14DV08145 | Complian | 09/30/2014 | N/A | DNR_VIOL | Sign | |
T15DV00303 | Complian | 01/20/2015 | N/A | DNR_VIOL | sign violation | |
T15DV05560 | Complian | 07/28/2015 | N/A | #184 | DNR_VIOL | Happy Wok in Unit #184 has a new banner dangling down from the storefront overhang. |
T18DV03274 | Noverify | 06/07/2018 | N/A | DNR_VIOL | : Abandoned Diesel trailer | |
T21DV01801 | Complian | 04/01/2021 | N/A | DNR_VIOL | Work without permits - TFD found second consultation room in pharmacy area not on the approved 2011 Plans for TI. |