Inspection History Details
Inspection Status: In Field Accepted
Inspection History: TWPE Daily Field Inspection
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/17/2026 | TWPE Daily Field Inspection | In Field Accepted | I facilitated precon with reps from Tucson Water, Tucson Airport, Ashton, esp and Days Excavating. Contact sheet is attached. Days will work monday to Thursday 6-4pm. After the survey is complete Matthew will send me the sib analysis and cut sheets. I will will schedule mock shutdown work orders. TW Chris Rodgers informed group that they can elect to perform shutdown for tie ins per updated AD. Ashton is removed concrete to prep for excavation which will start on tuesday. | |
| 06/23/2026 | TWPE Daily Field Inspection | In Field Accepted | I met w Rodney from Days Excavating. We received material delivery which I inspected. They began digging trench and laid 40 feet of 6inch DIP. Trench depth is 5’8 feet. They used bedding sand and bury tape. They will backfill tomorrow. | |
| 06/24/2026 | TWPE Daily Field Inspection | In Field Accepted | Days laid pipe to station 8+96.35. Tracer wire, bedding sand, bury tape were all installed. Compacted was completed per spec. I met with maintenance to exercise valves and prep for mock shut down. |
|
| 06/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Days trenched and installed pipe to station 10+33.97. Tee and gate valves were installed. ARV and 45’s will be installed tomorrow. Days will prep for pressure test tomorrow. | |
| TWPE Daily Field Inspection | Scheduled |