Permit: TW-CONS-0426-0066

Parcel: 14043011A


Addresses:

Inspection Status: In Field Accepted

Inspection History: TWPE Daily Field Inspection

Date Description Inspector Results Comments
05/14/2026 TWPE Daily Field Inspection In Field Accepted completed pre con, gathered contact information and performed mock shut down to confirm shut down. crew will work 8-12 hour days.
05/18/2026 TWPE Daily Field Inspection In Field Accepted Herman located 6” Ac pipe at each end of station 22 and prepped for shut down tomorrow. They will cut pipe and begin 2-3 day shut down for meter assembly installation. Herman also bolted fittings, flanges and broke off megalugs.
05/19/2026 TWPE Daily Field Inspection In Field Accepted We performed shutdown at 0900. Herman broke AC pipe and removed existing meter assembly and backflow preventer. they assembled 6” meter assembly and tied to existing pipe. They took elevations, wrapped pipe, taped tracer wire and backfilled. thrust blocks were poured.
TWPE Daily Field Inspection Scheduled