| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| TWPE Daily Field Inspection | Scheduled | |||
| TWPE Daily Field Inspection | Scheduled | |||
| 08/03/2026 | TWPE Daily Field Inspection | In Field Accepted | First day on jobsite.. | |
| 07/30/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/07/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/10/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/12/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/13/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/14/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/17/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/18/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/19/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/21/2026 | TWPE Daily Field Inspection | In Field Accepted | More testing on controls required. | |
| 08/21/2026 | TWPE Daily Field Inspection | Not Applicable | ||
| 08/25/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/26/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor is at 35% complete. | |
| 08/27/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 08/28/2026 | TWPE Daily Field Inspection | In Field Accepted | Contractor installed 115’+/- at Hampton to get it close to tie in point. All work completed was approved and accepted. | |
| 08/31/2026 | TWPE Daily Field Inspection | Not Applicable | Rain day. | |
| 09/01/2026 | TWPE Daily Field Inspection | Not Applicable | Dry out day, no activity. | |
| 09/02/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/03/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/04/2026 | TWPE Daily Field Inspection | In Field Accepted | Inspector Albert Soto will be on leave toady, I will cover this project in his absence. I met with Arles with Hunter this morning, he will have his crew work on WS private plumbing on Hampton and on Olive St. |
|
| 09/08/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/09/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/10/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/11/2026 | TWPE Daily Field Inspection | In Field Accepted | Pavement patching | |
| 09/14/2026 | TWPE Daily Field Inspection | Not Applicable | No activity today. | |
| 09/16/2026 | TWPE Daily Field Inspection | Not Applicable | No activity today. | |
| 09/17/2026 | TWPE Daily Field Inspection | Not Applicable | No activity today. | |
| 09/18/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/21/2026 | TWPE Daily Field Inspection | In Field Accepted | Installed fire hydrant. | |
| 09/22/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 09/24/2026 | TWPE Daily Field Inspection | Not Ready | Waterline on Hampton not holding pressure, pre-testing | |
| 09/25/2026 | TWPE Daily Field Inspection | Not Applicable | HCS repair at 227 E. Olive St. | |
| 09/28/2026 | TWPE Daily Field Inspection | Not Applicable | Looking for leak. | |
| 09/29/2026 | TWPE Daily Field Inspection | Not Applicable | Rain day, no activity. | |
| 09/30/2026 | TWPE Daily Field Inspection | Not Applicable | Still looking for leak on Hampton. | |
| 10/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Found and fixed water leaks. | |
| 10/02/2026 | TWPE Daily Field Inspection | Not Ready | Working on pressurizing waterline for test. | |
| 10/05/2026 | TWPE Daily Field Inspection | Failed | Loss of 2 psi in 2 hrs. will retest tomorrow. | |
| 10/21/2026 | TWPE Daily Field Inspection | In Field Accepted | Backfill to be completed tomorrow. | |
| 10/22/2026 | TWPE Daily Field Inspection | In Field Accepted | Asphalt patching and clean up tomorrow, sweep and clean streets on Saturday. | |
| 10/23/2026 | TWPE Daily Field Inspection | In Field Accepted | Asphalt trench patching and streets swept. | |
| 10/26/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 10/27/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 10/28/2026 | TWPE Daily Field Inspection | In Field Accepted | Valve box adjustments and concrete collars. | |
| 10/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Valve box adjustments. | |
| 10/30/2026 | TWPE Daily Field Inspection | Not Applicable | Rain day. | |
| 11/02/2026 | TWPE Daily Field Inspection | Not Applicable | Drying out from weekend rain. | |
| 11/03/2026 | TWPE Daily Field Inspection | In Field Accepted | Valve adjustments and concrete collars. | |
| 11/04/2026 | TWPE Daily Field Inspection | In Field Accepted | Preparation of trench crossings for asphalt patches. | |
| 11/05/2026 | TWPE Daily Field Inspection | In Field Accepted | More asphalt patching for tomorrow. | |