Inspection Status: In Field Accepted
Inspection History: TWPE Summary review of Daily Field Inspections
| Date |
Description |
Inspector |
Results |
Comments |
| 05/06/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
|
| 05/28/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
Action laid pipe to station 114+0. |
| 07/24/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
Action didn’t work this week. kinder morgan and swg are working on their line. |
| 07/31/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
ACTION installed two services at stations 112+78.56. one was a ARV and one was a service. |
| 08/14/2026 |
TWPE Summary review of Daily Field Inspections |
|
In Field Accepted |
Action completed pressure test on 8/13/26. Line tested at 200 psi from 1030-1230 and passed. There was zero loss. Action will prep for high cl2 test on 8/17/2026 at 0900. |
|
TWPE Summary review of Daily Field Inspections |
|
Scheduled |
|