Inspection History Details
Inspection Status: In Field Accepted
Inspection History: TWPE Daily Field Inspection
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/05/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 05/07/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 05/11/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 05/12/2026 | TWPE Daily Field Inspection | In Field Accepted | HB laid pipe to station 120+0.0. 1’ dip section under electrical line. Trench was backfilled and compacted to spec. | |
| 05/13/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 05/14/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 05/15/2026 | TWPE Daily Field Inspection | In Field Accepted | Action is cleaning up temp patch from the pipe installation. no excavation was performed today. | |
| 05/18/2026 | TWPE Daily Field Inspection | In Field Accepted | laid 8” dip to station 122+25.0. Action will start saw cutting for east 8” dip that’s replacing 3” mainline starting south of Illinois. | |
| 05/20/2026 | TWPE Daily Field Inspection | In Field Accepted | Action connected to new Tee at station 108+99.49. Gate valve was installed at station 108+90.50 and laid paid to station 110.00.00. Cathodic protection verified. | |
| 05/22/2026 | TWPE Daily Field Inspection | In Field Accepted | Action trenched and laid pipe to 123+50.0. They saw cut to Tennessee st. Pipe has backfilled and compacted to spec. Tito stated that Action will not work on Monday. | |
| 05/26/2026 | TWPE Daily Field Inspection | In Field Accepted | Action laid pipe to station 113+0.0. Dip section was installed at 112+78.98. 45 was used at dip section. Tito will update plans and elevations. | |
| 05/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Action laid pipe to station 116+69.52. They prepped pipe for installation on 6/1/16. | |
| 06/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Action laid pipe to station station 114+0. | |
| 06/03/2026 | TWPE Daily Field Inspection | In Field Accepted | Action laid pipe to station 119+50.0 | |
| 06/04/2026 | TWPE Daily Field Inspection | In Field Accepted | Action laid pipe to station 120+03.89. Gate valves and 8x6 Tee were installed at station 119+86.12. Mainline was 14 inches under electrical line. Megalugs were visually broken off. TOP to final grade is 63” |
|
| 06/08/2026 | TWPE Daily Field Inspection | In Field Accepted | Action laid pipe to station 122+0. | |
| 06/09/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 06/11/2026 | TWPE Daily Field Inspection | In Field Accepted | Action potholed to locate utilities. They will continue excavating tomorrow. | |
| 06/12/2026 | TWPE Daily Field Inspection | In Field Accepted | ||
| 06/15/2026 | TWPE Daily Field Inspection | In Field Accepted | Action got rained out and didn’t work today. | |
| 06/16/2026 | TWPE Daily Field Inspection | In Field Accepted | Action dug trench to station 124+50. They had to have southwest gas cut out two abandoned 8” gas mains. Vac truck potholled and located all utilities. Trench is 10’ deep and has shoring. | |
| 06/18/2026 | TWPE Daily Field Inspection | In Field Accepted | Action pumped out water and clean out trench. They installed a 45 at station 123+42.13. The south end of the trench was unstable so Tito dug out unstable dirt and backfilled with AB. They compacted with the intention of redigging trench to ensure safe trench/ work environment. Trench is 10’ deep. | |
| 06/19/2026 | TWPE Daily Field Inspection | In Field Accepted | ACTION set up shoring and installed a 20’ stick of 8” DIP. They installed cathodic protection and broke off megalugs. They used bedding sand, backfilled and compacted in 1’ lifts. They plated south end of trench so they can 45 on Monday. | |
| 06/22/2026 | TWPE Daily Field Inspection | In Field Accepted | Action potholed to locate gas mains and then backfilled. They didn’t lay pipe. | |
| 06/23/2026 | TWPE Daily Field Inspection | In Field Accepted | Action trenched to station 123+99.92. They had to relocate gas main after backfill. | |
| 06/24/2026 | TWPE Daily Field Inspection | In Field Accepted | Action installed FH at station 123+99.92. They installed sac anode and cathodic protection. They installed shoring and used trench box while assembling fire hydrant. | |
| 06/25/2026 | TWPE Daily Field Inspection | In Field Accepted | action dug trench and laid pipe to station 124.50. they used trench box and shoring. southwest gas inspected their mainline. | |
| 06/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Action backfilled and compacted trench from the pipe they installed last week. They dug trench and laid pipe to station 124+50. | |
| 06/30/2026 | TWPE Daily Field Inspection | In Field Accepted | Action trenched to station 124+89 to the 8inch tie in point. They used shoring equipment through out job. They will excavation on west time tomorrow. | |
| 07/01/2026 | TWPE Daily Field Inspection | In Field Accepted | Action backfilled trench and compacted in 1 ft lifts. | |
| 07/09/2026 | TWPE Daily Field Inspection | In Field Accepted | Action installed 8” DIP to station 125+50. They used shoring, tracer wire and bury tape. | |
| 07/10/2026 | TWPE Daily Field Inspection | In Field Accepted | Due to weather and muddy conditions, Action removed plates and backfilled excavation site at station 123+00. | |
| 07/20/2026 | TWPE Daily Field Inspection | In Field Accepted | Action did not work today. southwest gas is potholing to locate line so they can cover it w a liner. | |
| 07/28/2026 | TWPE Daily Field Inspection | In Field Accepted | Action potholed to connect tee to install FH at station 108+96.05. | |
| 07/29/2026 | TWPE Daily Field Inspection | In Field Accepted | Action installed air release valves at stations 113+17.97 and 113+49.77. | |
| 07/30/2026 | TWPE Daily Field Inspection | Canceled | ||
| 08/07/2026 | TWPE Daily Field Inspection | In Field Accepted | Action installed final ARVs at station 123+00. They will fill lines and perform pre pressure test Monday. | |
| 08/17/2026 | TWPE Daily Field Inspection | In Field Accepted | Action prepped line for high cl2 test. test was taken at 0900. 120+ ppm cl2 | |
| TWPE Daily Field Inspection | Scheduled |