Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: In Field Accepted

Inspection History: TWPE Daily Field Inspection

Date Description Inspector Results Comments
05/05/2026 TWPE Daily Field Inspection In Field Accepted
05/07/2026 TWPE Daily Field Inspection In Field Accepted
05/11/2026 TWPE Daily Field Inspection In Field Accepted
05/12/2026 TWPE Daily Field Inspection In Field Accepted HB laid pipe to station 120+0.0. 1’ dip section under electrical line. Trench was backfilled and compacted to spec.
05/13/2026 TWPE Daily Field Inspection In Field Accepted
05/14/2026 TWPE Daily Field Inspection In Field Accepted
05/15/2026 TWPE Daily Field Inspection In Field Accepted Action is cleaning up temp patch from the pipe installation. no excavation was performed today.
05/18/2026 TWPE Daily Field Inspection In Field Accepted laid 8” dip to station 122+25.0. Action will start saw cutting for east 8” dip that’s replacing 3” mainline starting south of Illinois.
05/20/2026 TWPE Daily Field Inspection In Field Accepted Action connected to new Tee at station 108+99.49. Gate valve was installed at station 108+90.50 and laid paid to station 110.00.00. Cathodic protection verified.
05/22/2026 TWPE Daily Field Inspection In Field Accepted Action trenched and laid pipe to 123+50.0. They saw cut to Tennessee st. Pipe has backfilled and compacted to spec. Tito stated that Action will not work on Monday.
05/26/2026 TWPE Daily Field Inspection In Field Accepted Action laid pipe to station 113+0.0. Dip section was installed at 112+78.98. 45 was used at dip section. Tito will update plans and elevations.
05/29/2026 TWPE Daily Field Inspection In Field Accepted Action laid pipe to station 116+69.52. They prepped pipe for installation on 6/1/16.
06/01/2026 TWPE Daily Field Inspection In Field Accepted Action laid pipe to station station 114+0.
06/03/2026 TWPE Daily Field Inspection In Field Accepted Action laid pipe to station 119+50.0
06/04/2026 TWPE Daily Field Inspection In Field Accepted Action laid pipe to station 120+03.89.

Gate valves and 8x6 Tee were installed at station 119+86.12. Mainline was 14 inches under electrical line.

Megalugs were visually broken off. TOP to final grade is 63”
06/08/2026 TWPE Daily Field Inspection In Field Accepted Action laid pipe to station 122+0.
06/09/2026 TWPE Daily Field Inspection In Field Accepted
06/11/2026 TWPE Daily Field Inspection In Field Accepted Action potholed to locate utilities. They will continue excavating tomorrow.
06/12/2026 TWPE Daily Field Inspection In Field Accepted
06/15/2026 TWPE Daily Field Inspection In Field Accepted Action got rained out and didn’t work today.
06/16/2026 TWPE Daily Field Inspection In Field Accepted Action dug trench to station 124+50. They had to have southwest gas cut out two abandoned 8” gas mains. Vac truck potholled and located all utilities. Trench is 10’ deep and has shoring.
06/18/2026 TWPE Daily Field Inspection In Field Accepted Action pumped out water and clean out trench. They installed a 45 at station 123+42.13. The south end of the trench was unstable so Tito dug out unstable dirt and backfilled with AB. They compacted with the intention of redigging trench to ensure safe trench/ work environment. Trench is 10’ deep.
06/19/2026 TWPE Daily Field Inspection In Field Accepted ACTION set up shoring and installed a 20’ stick of 8” DIP. They installed cathodic protection and broke off megalugs. They used bedding sand, backfilled and compacted in 1’ lifts. They plated south end of trench so they can 45 on Monday.
06/22/2026 TWPE Daily Field Inspection In Field Accepted Action potholed to locate gas mains and then backfilled. They didn’t lay pipe.
06/23/2026 TWPE Daily Field Inspection In Field Accepted Action trenched to station 123+99.92. They had to relocate gas main after backfill.
06/24/2026 TWPE Daily Field Inspection In Field Accepted Action installed FH at station 123+99.92. They installed sac anode and cathodic protection. They installed shoring and used trench box while assembling fire hydrant.
06/25/2026 TWPE Daily Field Inspection In Field Accepted action dug trench and laid pipe to station 124.50. they used trench box and shoring. southwest gas inspected their mainline.
06/29/2026 TWPE Daily Field Inspection In Field Accepted Action backfilled and compacted trench from the pipe they installed last week. They dug trench and laid pipe to station 124+50.
06/30/2026 TWPE Daily Field Inspection In Field Accepted Action trenched to station 124+89 to the 8inch tie in point. They used shoring equipment through out job. They will excavation on west time tomorrow.
07/01/2026 TWPE Daily Field Inspection In Field Accepted Action backfilled trench and compacted in 1 ft lifts.
07/09/2026 TWPE Daily Field Inspection In Field Accepted Action installed 8” DIP to station 125+50. They used shoring, tracer wire and bury tape.
07/10/2026 TWPE Daily Field Inspection In Field Accepted Due to weather and muddy conditions, Action removed plates and backfilled excavation site at station 123+00.
07/20/2026 TWPE Daily Field Inspection In Field Accepted Action did not work today. southwest gas is potholing to locate line so they can cover it w a liner.
07/28/2026 TWPE Daily Field Inspection In Field Accepted Action potholed to connect tee to install FH at station 108+96.05.
07/29/2026 TWPE Daily Field Inspection In Field Accepted Action installed air release valves at stations 113+17.97 and 113+49.77.
07/30/2026 TWPE Daily Field Inspection Canceled
08/07/2026 TWPE Daily Field Inspection In Field Accepted Action installed final ARVs at station 123+00. They will fill lines and perform pre pressure test Monday.
08/17/2026 TWPE Daily Field Inspection In Field Accepted Action prepped line for high cl2 test. test was taken at 0900. 120+ ppm cl2
08/24/2026 TWPE Daily Field Inspection In Field Accepted action completed tie in on Tennessee and CONTRACTOR’s way intersection. Pipe was wrapped, exothermic welds were completed. Tracer wire was ran along pipe. They backfilled and compacted trench and flushed fire hydrant. supervisor TITO stated our second tie in might be next Monday.
08/25/2026 TWPE Daily Field Inspection In Field Accepted I picked up meters and fittings from the north Stores and delivered them to Action‘s warehouse. Supervisor TITO reviewed plans for the tie in at sundt booster site. Tie in will be scheduled for next week.
08/27/2026 TWPE Daily Field Inspection In Field Accepted action installed all four water meters and set meter boxes. I spoke with supervisor TITO regarding the ties on Illinois. Tomorrow there will be a teams meeting to review the tires for some booster in Illinois.
08/28/2026 TWPE Daily Field Inspection In Field Accepted I attended teams meetings facilitated byTariq to review tie in schedule. Action installed 3 ARV stations and poured 2 concrete collars around gate valves.
09/01/2026 TWPE Daily Field Inspection In Field Accepted I spoke with supervisor TITO from Action. I informed him that he has to downsize the meter change outs He did last week to 5/8 inch meters. Action is currently using a vac truck to remove water from the intersection for the Illinois and CONTRACTOR’s way tie. If it does not rain tonight, Action will excavate tomorrow morning to prep TIE IN.
09/02/2026 TWPE Daily Field Inspection In Field Accepted action installed 8 inch Tee with gate valves and one stick of 8 inch ductal iron pipe at station 108+38.33. Action ran tracer wire, used bury tape and compacted Dirt during backfill. All mega lugs were visually broken off.
09/03/2026 TWPE Daily Field Inspection In Field Accepted action installed 8 inch T and gate valves at station 108+88. 99. They also installed the 8“ x 45° bend at station 108+87. 16. Exothermic welds were performed and sacrificial anode was installed. Tracer wire and bury tape was installed. They backfilled with betting Sands and supported Southwest gas mainline the backfilled to spec and perform temporary patch..
09/04/2026 TWPE Daily Field Inspection In Field Accepted action completed temporary patch on Illinois and contractors way intersection. They set 3 water meters. I took the Pueblo work orders and old meters to the Meter Shop and emailed the team that the meter changes were completed.
09/09/2026 TWPE Daily Field Inspection In Field Accepted action installed dip section under the gas main at the intersection of CONTRACTOR’s way and Illinois Avenue. Cathodic protection was installed. Tomorrow we will complete one time connecting the 8 inch DIP to the 4 inch asbestos cement pipe on Illinois.
09/10/2026 TWPE Daily Field Inspection In Field Accepted action completed both ties on CONTRACTOR’s way in Illinois Street.
09/17/2026 TWPE Daily Field Inspection In Field Accepted I met up with the utility technicians to locate valves, exercise valves and to perform a mini mock shut down for the sundt booster station. The mock shut down failed. Action called in a blue steak with the purpose to Locate a buried butterfly valve. I will meet with the UT’s tomorrow to continue to look for valves.
09/24/2026 TWPE Daily Field Inspection In Field Accepted I spoke with project manager and engineer Tariq to review changes to the tie in at sundt booster site. Action will replace remaining asbestos cement pipe and install gate valves and Tee. TITO from Action excavate tie in stations to get a visual to prepare for tie in. TEP confirmed that they will run off of the 48 inch line in zone D.
09/28/2026 TWPE Daily Field Inspection In Field Accepted Action completed the tie for zone C and zone D at the sundt booster site. All duct iron pipe was wrapped had tracer wire and had three-way connectors installed. Action backfield and compacted excavation site at the Tee for zone D.
09/30/2026 TWPE Daily Field Inspection In Field Accepted action backfilled excavation sites for zone c and d tie ins. Once it stops raining, they will replace the last stick of asbestos cement pipe to cadet the bypass for zone C and D.
10/01/2026 TWPE Daily Field Inspection In Field Accepted Action installed 30 feet of 8 inch DIP to connect zones c and d. Exothermic welds and sacrificial anodes were installed. They backfilled and compacted in 1 foot lifts. Peak corrosion performed pre-continuity test.
10/23/2026 TWPE Daily Field Inspection In Field Accepted action completed the fourth air relief valve and framed base for concrete. Action will pour concrete next week around arv and gate valve risers.
10/26/2026 TWPE Daily Field Inspection In Field Accepted Action completed fourth and final ARV.
11/04/2026 TWPE Daily Field Inspection In Field Accepted action completed the tie for zone D. They use exothermic welds and broke off all the mega lugs. They backfilled and compact trench to spec.
TWPE Daily Field Inspection Scheduled