Permit: TR-UTL-0326-00463

Parcel: 113070220


Addresses:

1601 E GLENN ST

Inspection Status: Passed

Inspection History: TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting

Date Description Inspector Results Comments
05/05/2026 TRSP - ROW - Pre-Activity Field/Pre-Construction Meeting Passed Script read 2nd pre-con for country club in Glenn for the tie in they're gonna be doing on the 20th and 21st at country club and Glenn this project is a continuation for the final gas up and backfill they will be needing a total of six days to do this starting on the 18th all the way up and down Glenn for the gas up in Tie ins this potentially includes the backfill as well. They should be done with this project by the middle of June if they stay on schedule.