| 09/15/2025 |
TRSP - ROW - Backfill - Placement/Compaction |
|
Re-inspection required |
Work is still in progress, plated trench still open across Concord St |
| 09/25/2025 |
TRSP - ROW - Backfill - Placement/Compaction |
|
Passed |
Backfilled with AB with compaction texting being performed by a third party. I asked for the compaction tests to be emailed to me so I can add them to the final inspection. Will mentioned that pavement patch will be sometime around Wednesday of next week 10/01/25 |