Inspection Status: Not Ready
Inspection History: TRSP - ROW - Concrete - Acceptance (Post-Pour)
| Date |
Description |
Inspector |
Results |
Comments |
| 06/26/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Not Ready |
onsite meeting with Rudy, job hasn’t started yet. Current permit set to expire next week, extension request to be submitted. |
| 07/22/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Complete (Recurring) |
first section of driveway, curb radius completed, aiming for sidewalk, ramps, and driveway apron to be poured before end of week |
| 07/24/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Complete (Recurring) |
more vertical curb has been completed. Ramps, sidewalks, and apron pouring this weekend. |
| 07/28/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Partial Pass |
|
| 08/12/2026 |
TRSP - ROW - Concrete - Acceptance (Post-Pour)
|
|
Complete (Recurring) |
ramp on east side needs joints between ramp and curb, curb needs to slope in line with ramp to avoid trip hazard, out of spec ramp cross slope will need entire ramp redone, truncated domes aligned to avoid gaps. |