Permit: TR-PIA-1124-00018

Parcel: 14028012A


Addresses:

6219 S SEARS BL

Inspection Status: Passed

Inspection History: TRSP - PIA - AB Placement

Date Description Inspector Results Comments
09/05/2025 TRSP - PIA - AB Placement Passed Today Trystan and I took a sample from a pile of AB from Vulcan because the AB from PnP did not get an approval from the lab. Stringline and density of sub grade on Monday, stringline and density of AB on Thursday.
09/11/2025 TRSP - PIA - AB Placement Passed The AB and roadway were tested and passed for compaction as well as string lined (@2.5") to ensure paving can occur the next day.
10/10/2025 TRSP - PIA - AB Placement Passed Today the AP is being graded and watered.
10/17/2025 TRSP - PIA - AB Placement Passed Due to the heavy rains over the weekend Bubba decided to open up the AB and let the subgrade dry out for a few days. As of today they are still processing the AB back into grade. String line and densities will probably be next week.
10/23/2025 TRSP - PIA - AB Placement Passed String lined all three roadways that make up Cielo Reserve. All areas were within the .02' tolerance, and the density tests were all at or above 100% for compaction tested with nuclear device.
10/29/2025 TRSP - PIA - AB Placement Passed AB placement is complete