Inspection Status: Passed
Inspection History: TRSP - PIA - Sidewalk Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 02/06/2026 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
Contractor is very close to finishing all sidewalk portions that fall within the scope of the PIA permit. Contractor will be scheduling a final walk-through in the very near future |
| 02/12/2026 |
TRSP - PIA - Sidewalk Placement |
|
Passed |
All sidewalk pertaining to the PIA portion of the Cielo reserve subdivision has been completed. The site is ready for a final walk-through, and this inspection is no longer needed. |