Inspection Status: Partial Pass
Inspection History: TRSP - PIA - AB Placement
| Date |
Description |
Inspector |
Results |
Comments |
| 06/02/2026 |
TRSP - PIA - AB Placement |
|
Partial Pass |
Nuclear Density tests on AB |
|
TRSP - PIA - AB Placement |
|
Scheduled |
|
| 06/05/2026 |
TRSP - PIA - AB Placement |
|
Passed |
AB Nuclear Density Tests - We were able to achieve 100% compaction with a nuclear device at four separate locations (Apodaca Dr, Carranza Dr, Adam Buckner Dr, and Dionicio Dr). The moisture was almost at optimum due to the water truck constantly cruising around and keeping the material moistened. The grade and elevation is close to where it needs to be and should be string lined on Monday, June 8th. |