Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: TRSP - PIA - AB Placement

Date Description Inspector Results Comments
06/02/2026 TRSP - PIA - AB Placement Partial Pass Nuclear Density tests on AB
TRSP - PIA - AB Placement Scheduled
06/05/2026 TRSP - PIA - AB Placement Passed AB Nuclear Density Tests - We were able to achieve 100% compaction with a nuclear device at four separate locations (Apodaca Dr, Carranza Dr, Adam Buckner Dr, and Dionicio Dr). The moisture was almost at optimum due to the water truck constantly cruising around and keeping the material moistened. The grade and elevation is close to where it needs to be and should be string lined on Monday, June 8th.